Entry   Status report after dispatch meeting Monday 27.5. 09.30 , posted by Gerd Wellenreuther on 27 May 2019, 10:35 
SPB/SFX


Digitizers are ready, have been tested by CAS ==> to be be installed / integrated probably next week ==> according to Adrian probably
Monday, to be confirmed with AE (Bruno + Hamed) ==> is confirmed to be today
Different GUIs were reporting varying values
Entry   Status report after dispatch meeting Friday 24.5. 09.00, posted by Gerd Wellenreuther on 24 May 2019, 11:01 
SPB/SFX


are working on achieving a good focus @ 6 keV, which currently is not as good as expected. ==> This is understood now, those
were higher harmonics, too many absorbers in the beam. Absorber still shows some structure, though
Digitizers are ready, have been
Entry   Minutes of the Technical integration meeting 22.05.19, posted by Gerd Wellenreuther on 22 May 2019, 09:58 
FXE

SPB/SFX


XTD2 attenuator appears to be damaged.
Beam at lower energies look disturbed, SPB/SFX will contact
Entry   Status report after dispatch meeting Monday 20.5. 09.30, posted by Gerd Wellenreuther on 20 May 2019, 10:02 
SPB/SFX


are working on achieving a good focus @ 6 keV, which currently is not as good as expected.
Digitizers are ready, have been
tested by CAS ==> to be be installed / integrated probably next week
Different GUIs were reporting varying values for STATUS on different
Entry   Status report after dispatch meeting 09.00, posted by Adriano Violante on 17 May 2019, 10:47 
SPB/SFX


ADC have been requested. HW should be already installed (SPB to check). BF will discuss with SPB how to proceed.


FXE


LPD is running.


​SQS
Entry   Minutes of the Technical integration meeting 15.05.19 , posted by Adriano Violante on 15 May 2019, 12:53 
SPB/SFX


Nano KB mirrors and CSS controls are OK
Digitizers have been requested. HW needs to be installed and set up and the timeline
has to be clarified betweek BF and SPB. Not possible to have them running on short notice.

Comment from AS: Trigger Test with pulse on
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 13 May 2019, 11:24 
SPB/SFX


The gear ratio of the CSS is unclear but this was already known and discussed with SPB/SFX ==> AL is working on it toghter with AE.


FXE


Karabo for Jungfrau detector has been udpated and works fine. For the LPD some issues were reported but SH commented that the problems
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 10 May 2019, 10:52 
SPB/SFX


IRDa commissioning successful. A. Mancuso thanked all the people involved in the project. 
The gear ratio of the
CSS is unclear but this was already known and discussed with SPB/SFX
Mirrors motors had some issues (ELMO motors), they are already been fixed.
Adam
Entry   Minutes of the Technical integration meeting 08.05.19 , posted by Adriano Violante on 08 May 2019, 10:10 Technical_Integration_Meeting_07.05.2019_-_Copy.pptx
SPB/SFX


IRDa commissioning ongoing. 
CSS. Limit switches re cabling is ongoing. For the next run the old configuration will
still be used. RB and MS will meet to make sure the system can be safely (from the component point of view) operated. ==> Solved.
Comment
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 06 May 2019, 10:20 
SPB/SFX


IRDa commissioning ongoing. 
For this week AGIPD works and re commissioning of the nanometer mirrors will be perfermed.
It is possible that support from AE will be required.
CSS. Limit switches re cabling is ongoing. For the next run the old configuration will
Entry   Report after dispatch meeting 9:00, posted by Adriano Violante on 03 May 2019, 14:07 
SPB/SFX


IRDa commissioning ongoing. First images have been taken with the Jungfrau detector. Possible to record using 7 to 8 memory cells,
after that there are issues. CAS is having a look. 
CRL motors being tested. --> issue with a CRL motor is being addressed (connector
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 29 Apr 2019, 10:04 
SPB/SFX


IRDa commissioning ongoing. Focus (<5um) in the second interaction region has been achieved.
CRL motors being tested.
--> issue with a CRL motor is being addressed (connector issue). 
AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
Jungfrau
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 26 Apr 2019, 12:28 
SPB/SFX


IRD commissioning ongoing.
CRL motors being tested. --> Mechanical issue with a CRL motor is being addressed.
CSS
interlock tests with AE still ongoing.
AE needs to know when Loop 9 and 10 are expected to run. SPB to check.
Jungfrau detector:
Entry   Minutes of the Technical integration meeting 24.04.19 , posted by Gerd Wellenreuther on 24 Apr 2019, 10:05 
SPB/SFX


SPB/SFX is preparing for the upcoming beamtime.
CRL motors being tested. --> Still ongoing.
CSS interlock tests
being planned for tomorrow. --> Still ongoing.
AE needs to know when Loop 9 and 10 are expected to run. SPB to check.


​FXE
Entry   Minutes of the Technical integration meeting 17.04.19 , posted by Adriano Violante on 17 Apr 2019, 11:34 
SPB/SFX


CRL motors being tested. Today BB (AE) will check the status.
CSS interlock tests being planned for tomorrow.
Jungfrau
motors -  SS (EET) fixed some cable issues. Now ok.
Julabo chiller: loop 5 has been updated (interlocks definition, setpoints...) AE+DET
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 15 Apr 2019, 09:55 
SPB/SFX


Tomorrow set up of the donwstream interaction region will start.
Jungfrau calibration pipeline has to be pushed. ITDM and
DET involved. Can be done this week.
Additional motors control bein implemented by AE.
Request presented to CAS to resume a project
Entry   Status report after dispatch meeting 09.30, posted by Adriano Violante on 12 Apr 2019, 10:41 
SPB/SFX


Hercules students period. During the night a pump failed and recovered after a power cycle.
5Hz mode tests were performed
and successful
CSS being commissioned. X mov elmo stage still has to be configured. Will be done probably today.
After some updates,
Entry   Minutes of the Technical integration meeting 10.04.19 , posted by Adriano Violante on 10 Apr 2019, 10:54 
SPB/SFX


CRL implementation in the hutch. Tests can start today.
CSS Test have been started. One elmo devide has to be implemented
today. Interlocks have to be tested (later).
AGIPD motion. Middle layer final tests will be done during next reconfiguration od the detector.
Julabo
Entry   Report after dispatch meeting 09.30, posted by Adriano Violante on 08 Apr 2019, 10:48 
SPB/SFX


5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in
SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen.
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 05 Apr 2019, 10:07 
SPB/SFX


5Hz mode tests started (SPB/SQS) and partially successful. A detailed report will be sent around. 2 cameras in SPB and digitizers in
SQS were tested. Cameras OK. Digitizers data recordin has some issues being fixed (train id related). Next week on Thursday a test with beam is foreseen.