General Announcement:
- The Work on the Controls Network are progressing very nicely;
- Work in the tunnels: safety practices due to Covid-19 were covered in the staff meeting.
The policy states that if two or more workers that are closer than 1.5m for longer than 15 min then both shall use FFP2 masks.
If shorter than 15 min (whole day), workers can use surgical masks.
- Work in tunnels with clean tents: in case of 2 simultaneous workers, by default they have to use PPE.
- FFP2 masks may not be suitable for clean room. More information will follow.
- For additional questions please contact SRP.
- Next Friday May 1st there will be no meeting. We resume this meeting series on Monday.
CTRL:
- Working on control network activities.
- Two trainings on the notification service were done. Another one will follow soon.
DA:
- Group is focusing in offline data analysis.
EEE:
- Normal OCD service will be open next week. However, there will be no OCD for micro-TCA issues.
- Up to 4 PLC staff on site to support groups – EEE is asking groups to find out what type of onsite people will be needed.
- EEE colleagues from technical side will also be available on site.
- EEE colleagues from fast electronics in principle will not be on site, unless requested and planned (mostly are doing only home-support).
- We rely on the instruments plans. Please provide such information to EEE.
VAC:
- Preparing for the re-start activities.
XPD:
- Preparing for re-start activities.
- XPD will receive a VAC chamber from Italy today and next week the group will work on it.
DET:
- Preparing a plan for activities together with instruments.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Preparing to switch on the lasers on next week.
- LAS do not need micro TCA support if balcony room works for us. Group just needs to receive the master time from the balcony.
EEE states that it shall be fine unless if things fails during the night. LAS comment in this case the laser will safely shutdown in the night.
SPB:
- A crashed loop will be taken care next week;
FXE:
- Nothing special to report.
MID:
- Preparing with EEE and CTRL for Monday re-start phase.
HED:
- Same as MID.
SCS:
- Preparing for next week.
SQS:
- Trying to start up and provide info to EEE. |