Group Selection Page HELP DOC Controls Group Data Analysis Group ITDM WP76 DET Vacuum XRO EEE WP78 WP74 FXE SCS SPB MID HED SQS SXP Sample Environment Photon Commissioning Team Operation PSPO XO TS
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 119     Entry time: 11 May 2020, 14:53
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 11.05.2020 
General Announcement:
- The proposed works on the Control network are fully organized for this week;
- Safety: The EuXFEL task force for the Covid-19 discussed this morning the safety issues here presented last Friday. 
On Mondays and Wednesdays there will be a SRP representative in this meeting to address related questions and on Fridays Tobias Haas will be attending. 
- General: there was a short notice from MKK2 regarding cooling maintenance in tunnels to be performed today. This short notice is a communication error. 
The task was a summer shutdown work anticipated to today and was not properly communicated. No EuXFEL group raised concerns to this activity taking place today. 
- General: 30% staff presence restrictions - so far it seems that this number is fine. Groups are encouraged to think if there is a need to increase this number,
especially in the instrument side. Please inform XO. 

CTRL:
- The tickets with requests to be carried out this week are all planned.
- Group is moving to more usual tasks with instruments and support groups.

DA:
- Planned activities are in progress.

EEE:
- There was no observed master time reset from the Desy side after the Covid-19 accelerator shutdown. 

VAC:
- Nothing to report.

XPD:
- Last week's planned activities went fine.
- It is agreed with VAC that on Wednesday one section of XTD9 will be vented, in preparation for an activity.

DET:
- Nothing special to report; DSSC pump/cooling issue is being taken care.

ITDM: 
- Nothing to report.

XRO:
- A test of a motor in a magnetic switch of a XTD6 mirror will be made this week - proper ticket will be send to CTRL.

LAS:
- SA1 PP-laser is OK; others are progressing. Work goes smooth.

SPB:
- Starting the instrument. All fine until now and this week there is a plan to test Detectors.

FXE:
- The works are going as planned.

MID:
- Continue with technical commissioning: activities under control.

HED:
- Nothing special - group placed tasks with Controls and also need help from EEE, all under control.

SCS:
- Minor issues while switching on the beamline: CTRL is informed and is taking care.

SQS:
- Ramping up the vacuum: so far all going well.
ELOG V3.1.4-7c3fd00