General Announcement:
- SA2 lasing: up to 2mJ@9keV was achieved with strong linear and quadratic tapering with 250pC bunch charge.
Lasing with 500pC achieved 0.45mJ@9keV and with 100pC achieved 0.75mJ@9keV.
- From today we start the summer shutdown phase.
- Please note the last minute information on air conditioning maintenance in tunnels between Tuesday 15:00 up to Wednesday 08:00.
We ask groups to shift planned works to outside this time slot. In case you need to be in tunnel, it is mandatory to use FFP2 masks.
CTRL:
- Karabo 2.9.0 deployment will start tomorrow and follow over the week. Typical activity time is from 8AM-16:00 each day.
DA:
- No problems.
EEE:
- EEE plans for tomorrow the mc2 migration.
VAC:
- HED mono has adjusted gap between crystals. All other tunnel activities ongoing.
XPD:
- Major task for the coming week is related to the PES maintenances. All other tasks are also organized.
DET:
- Will carry tests after the Karabo installation.
ITDM:
- Group will be busy with updates to be done this week.
XRO:
- Completed big shutdown activities: M3 cooling mirror - leak tested OK and pumping during the weekend.
LAS:
- All lasers are in operation.
SPB:
- Progressing with regular planned tasks.
FXE:
- Nothing to report.
MID:
- Nothing to add.
HED:
- Working with EEE activities.
- HED requests suitable dates for testing the THz laser. This date has to avoid infra-structure, interlock and other works.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |