Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 116     Entry time: 04 May 2020, 14:20
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 04.05.2020 
General Announcement:
- From today on there is no general restrictions in accessing the EuXFEL site: only consent of group leader is needed.
- Control Network activities: there is a sensible approach for this week and currently CTRL and XO do not observe issues needing discussions.
- Activities in tunnels start this week. We encourage the support groups to point any issue during this series of meetings or by sending an e-mail to xo@xfel.eu.

CTRL:
- A third training on the notification service will happen on Wednesday. Proper communication will be send around.

DA:
- Nothing to report.

EEE:
- Bringing up the systems.

VAC:
- Group members are on site to prepare activities. The main one this week is the installation of pre-shutter in XTD10. 
- Protective masks have to be picked up with SRP.

XPD:
- No incidents during last week. Two group members are currently working at EuXFEL site. 
Later additional staff will work on tunnels (e.g. on Hirex; on scintillator screen on IMG) and in the lab. 
- SRP has to provide protective equipment to the staff.

DET:
- Nothing to report.

ITDM: 
- We plan to perform tasks on the rack rooms and we are waiting for the SRP assessment.

XRO:
- Nothing to report.

LAS:
- Group has an on-site team who is switching on all lasers this week. 
An order for the re-start will be communicated after an evaluation of each system's condition.

SPB:
- Group has staff on site to start systems.

FXE:
- One team is onsite. The planned activities shall not involve other groups: re-starting systems and making tests in the control hutch.

MID:
- Plan is to bring the PLCs and electronics up.

HED:
- Starting lasers and split-delay line. Activities do not mix with other groups. 
- Group is coordinating with EEE for checking the rack rooms.

SCS:
- Not present.

SQS:
- Start being on site today and plans to re-start devices together with EEE.
- Also start setting up ion pumps (no need for VAC support).