Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 134
Entry time: 19 Jun 2020, 14:28
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 19.06.2020 |
|
|
General Announcement:
- Next Monday it is planned the NOT-AUS experiment in the frame of Interlock tests and the emergency off will be disabled.
Only groups with EQP persons can continue working in the hutches. An e-mail was sent by TS.
- There will be test on smoke extraction in Tunnels on next Monday and Tuesday. Information was sent to Readiness mailing list.
- An e-mail to Readiness list was sent this morning regarding TUV/Interlock tests in SASE areas on July 1-3:
No access or work on the experimental and optics hutches is allowed in these days. More specific details will follow in the coming week.
If you have questions, please contact XO.
CTRL:
- Finished 2.9 deployment - control rooms also have the updates;
- CTRL is working on the XGM together with Theo (XGM does not update some properties). This came after an update done at the Desy side.
DA:
- Nothing to report.
EEE:
- Shutdown activities are ongoing.
- Migration to mc2motors was ongoing. EEE encourage groups to check motors after start running again.
- For next week: cabling work in SCS and PLC modifications with the help of two external colleagues.
- Timing system update: SA1 and SA3 timing system laser and instruments are done; EEE will do the SA2 this afternoon; Still to be arranged a date for the balcony rooms.
If problems occur, please contact Bruno Fernandez.
VAC:
- Finished all shutdown activities.
- The recovery of HED pulse picker branch needs help of HED staff. HED points Konstantin is around today.
XPD:
- Finished all XPD tunnel works.
- Testing ongoing: SA2 motors after mc2 migration.
- Checking the trigger on uTCA crates after upgrade.
- DAQ test was successful with ITDM.
DET:
- New DAQ system has some issues with AGIPD in SPB (did not store data) - to be followed next week.
- Deployment of new calibrations is ongoing.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Warming up SA3 laser.
- SA1: LAS maintenance is not finished. So we ramp up later. Bruno reminds SA1 must be back and switched on again.
UNSYS:
- Enclosure of panels in SASE3 has been installed and all tunnel activities are done.
SPB:
- Nothing to report.
FXE:
- Works on Detectors are ongoing.
MID:
- Nothing special.
HED:
- Activity with lasers alignment.
SCS:
- Not present.
SQS:
- Nothing to report. Working in different things/parts.
- SQS has planned activities for July 1st-3rd. It suggests that more specific communication on TUV tests and access restrictions must be done differently
than the e-mail distributed on June 8th and today. XO will look for improvements. |