Group Selection Page
HELP
DOC
Controls Group
Data Analysis Group
ITDM
WP76
DET
Vacuum
XRO
EEE
WP78
WP74
FXE
SCS
SPB
MID
HED
SQS
SXP
Sample Environment
Photon Commissioning Team
Operation
PSPO
XO
TS
|
Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 124
Entry time: 25 May 2020, 15:29
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 25.05.2020 |
|
|
General Announcement:
- Machine started SA2 lasing last weekend. Currently photon energy is 0.5mJ at 9keV.
- CTRL OCD was called Friday on the SR slits position and movement. It was quickly solved.
- XO ask people who carries work in tunnels to use this meeting to raise questions and concerns.
- XO also ask people to discuss during this series of meetings possible resource conflicts among the support groups for the upcoming week(s).
CTRL:
- New Karabo version installed at MID is working nicely. Instrument staff is creating new panels with Karabo9 and CTRL hopes to integrate
this Karabo version in the whole facility during summer shutdown.
DA:
- Not present.
EEE:
- Working in normal duties.
- Cabling installation in SQS is done. The FXE installation has a mismatch with a rack planning (XGMD) and responsible company for installation
may come back on Wednesday to solve it.
VAC:
- Tunnel works are nicely ongoing.
XPD:
- Working on tunnels and looking at lasing in SA2.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- A water leakage in an amplifier box in SA1 laser occurred last Thursday. It is repaired but LAS will have to investigate on possible damages on optics
(due to water inside). Laser operation will be possible only tomorrow or at the end of the week. LAS will provide further details on Wednesday.
SPB:
- Nothing to report.
FXE:
- Nothing to add besides the cabling installation issue mentioned by EEE.
MID:
- New Karabo is working nicely up to now.
- Tunnels work is also finished; MID staff continues with work on the hutch/optics.
HED:
- No issues to report.
SCS:
- SCS will be busy with an external company and needs assistance of SRP on hot work permit. Sandra Plett will communicate with Michael Prollius.
- SCS has informed DET that there is data in the computer to be saved. DET is aware and has taken needed actions.
SQS:
- Nothing to report: activities are progressing normally. |