Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 133     Entry time: 18 Jun 2020, 13:40
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 17.06.2020 
General Announcement:
- Today and tomorrow it takes place the tunnel ventilation maintenance between 6:30 and 8:00AM;
- An e-mail was sent to readiness list with tunnel access restrictions for next Friday morning at the Osdorf Born site in and XTD4 work between 10-11AM.
- Today there the maintenance of the SA3 hutch crane is scheduled.

CTRL:
- CTRL will follow up the uTCA updates.
- Mc2 migration in SA2 is almost done - only XPD needs to test some componenents.
- CTRL is working in some layout problems in scenes of the latest GUI update (new Karabo). Groups are encouraged to write tickets to CTRL if they require changes. 

DA:
- Nothing to report.

EEE:
- Shutdown activities are ongoing with, e.g, VAC loop updates and PLC updates;
- The firmware updates affecting the PP-laser timing will take place on next Friday (19.06) in all SASEs. 
- EEE is following the delay on the MID cabling related to personal interlock. 

VAC:
- Shutdown activities in XTD6 and XTD10 are ongoing. 

XPD:
- Currently finishing own summer shutdown tasks in tunnels.
- First DAQ test together with ITDM: had to wait the timing server re-start. To be continued today also after full mc2 migration.

DET:
- Calibrations of detectors at instruments are ongoing.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- So far all in good state.

UNSYS:
- Nothing to report.

SPB:
- DAQ update was not an entire success - but it has been taken care. DAQ is needed for the calibration test of detectors.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing special.

SCS:
- Nothing to report.

SQS:
- PC updates are ongoing.
- SQS raises the question on hutch access during the disabled emergency off planned for next Monday. It is possible that SQS EQP will be in sick leave on that day. 
XO will contact Torsten Schoen to get more details on the time schedule and possible access for that day.