Entry   Notes XO Integration Meeting 23.06.2021, posted by Frederik Wolff-Fabris on 23 Jun 2021, 10:41 
General Announcement:
- In case groups had issues with power glitch on last Sunday, please let XO know for that this will be discussed with Desy.
- Interlock tests are happening and will reach the hutches on next week. In the past there is little to no implications to the instruments. 
Entry   Notes XO Integration Meeting 21.06.2021, posted by Frederik Wolff-Fabris on 21 Jun 2021, 10:56 
General Announcement:
- Interlock tests starting this week. An e-mail was sent to xo-info@xfel.eu and if clarifications are needed please get in touch with XO.
- Zunaira A. asks if XO knows if emergency OFF will be tested and power would be bridged. 
Entry   Notes XO Integration Meeting 16.06.2021, posted by Arvid Gebhardt on 16 Jun 2021, 08:37 
General Announcement:

- Interlock test next 2 weeks starting on monday - from next wednesday the photon tunnels will be closed; Tests are the XHEXP1 take place on
30.06, 01.07 and 02.07 with the last date as reserve; An email is going to be send by FWF to the xo-info@xfel.eu list.
Entry   Notes XO Integration Meeting 14.06.2021, posted by Frederik Wolff-Fabris on 14 Jun 2021, 10:15 
General Announcement:
-
Entry   Notes XO Integration Meeting 09.06.2021, posted by Frederik Wolff-Fabris on 09 Jun 2021, 10:14 
General Announcement:
- Zunaira A. says that on HED on Saturday there was the 2 hour break on the search mal-function. It was solved by manual restart done by Eric B. (origin
was the DACHS 
Entry   Notes XO Integration Meeting 07.06.2021, posted by Frederik Wolff-Fabris on 07 Jun 2021, 10:29 
General Announcement:
- Accelerator has been shutdown this morning and the Summer/21 maintenance period has started.
- A. Galler asks the instruments to check the beamlines are in safe state for that tuning and setup starts after the maintenance without potentially damaging
Entry   Notes XO Integration Meeting 02.06.2021, posted by Frederik Wolff-Fabris on 02 Jun 2021, 10:24 
General Announcement:
- XO reminds staff to check the safety trainings and the DACHS access rights/permissions for the tunnels when planning tunnel accesses during the maintenance
period. 
Entry   Notes XO Integration Meeting 31.05.2021, posted by Frederik Wolff-Fabris on 31 May 2021, 10:18 
General Announcement:
- Next Friday is the last User & Operation meeting for this run. We will have presentations of 3 user groups.
- Today 31.05 is a normal delivery beam day.
Entry   Notes XO Integration Meeting 26.05.2021, posted by Frederik Wolff-Fabris on 26 May 2021, 10:23 
General Announcement:
- XO reminds the procedure for ZZ access is organized through the PRC. 
If a ZZ is needed, please get in touch with the PRC for advice and fill it up the Redmine access request (link located at the TTfinfo e-log). 
Entry   Notes XO Integration Meeting 19.05.2021, posted by Frederik Wolff-Fabris on 19 May 2021, 10:13 
General Announcement:
- A. Galler says the Interlock Tests schedule is placed at the EUXFEL Infrastructure Calendar. 
Concerning the TUV tests at Schenefeld side, this happens between June 30th and July 2nd (the 2nd is a reserve date). When a detailed schedule is made,
Entry   Notes XO Integration Meeting 17.05.2021, posted by Frederik Wolff-Fabris on 17 May 2021, 10:25 
General Announcement:
- Adrian Mancuso tells on the workaround for the crosstalk between SA1/SA3 documented by Harald Sinn. The idea was to switch off the feedback prior the
bunch changes. 
Entry   Notes XO Integration Meeting 12.05.2021, posted by Arvid Gebhardt on 12 May 2021, 09:21 
General Announcement:

- User Operations Meeting takes place on next Friday 09:00.

CTRL:
Entry   Notes XO Integration Meeting 10.05.2021, posted by Frederik Wolff-Fabris on 10 May 2021, 10:05 
General Announcement:
- Two smoke sensors affected in SA3 triggering fire alarm: The first one could be reset but for the second one the reset did not work and fire brigade
was in. 
Entry   Notes XO Integration Meeting 05.05.2021, posted by Frederik Wolff-Fabris on 05 May 2021, 10:20 
General Announcement:
-  
Entry   Notes XO Integration Meeting 03.05.2021, posted by Frederik Wolff-Fabris on 03 May 2021, 10:06 
General Announcement:
- The deadline for submitting the summer maintenance tasks is ended. In case you have not done so, please submit it as soon as possible.
- Monica T. as DRC invites people to attend the DRC jour-fixe meeting.
Entry   Notes XO Integration Meeting 28.04.2021, posted by Frederik Wolff-Fabris on 28 Apr 2021, 10:04 
General Announcement:
- A. Galler points to the deadline for submitting summer maintenance task list on April 30th.
- XO would like to remind instruments that in case of operation failure related to Interlocks issue, please also include the PRCs (prc@xfel.eu) on the
Entry   Notes XO Integration Meeting 26.04.2021, posted by Frederik Wolff-Fabris on 26 Apr 2021, 11:08 
General Announcement:
- The deadline to submit the maintenance task list is on 30.04. We thank all the groups that have already submitted. In case of any question and comments,
please contact 
Entry   Notes XO Integration Meeting 21.04.2021, posted by Frederik Wolff-Fabris on 21 Apr 2021, 10:50 
General Announcement:
-  XO reminds on the deadline of 30.04 for submitting the Summer maintenance task lists. For this, please do so sending the list to xo-planning@xfel.eu.
Entry   Notes XO Integration Meeting 19.04.2021, posted by Frederik Wolff-Fabris on 19 Apr 2021, 11:39 
General Announcement:
-  Remind on the Summer maintenance period: deadline to submit task list is April 30th. XO invite all groups to submit by this date.
Entry   Notes XO Integration Meeting 14.04.2021, posted by Frederik Wolff-Fabris on 14 Apr 2021, 10:50 
General Announcement:
- We would like to remind groups that the deadline for submitting to XO the feedback on the planned activities for the Summer/21 maintenance time is on
April 30rd. 