General Announcement:

  •  

CTRL:

  • small intervention --> udpate of karabo-gui client exflagteway

DA:

  • maxwell gpfs software maintenance --> offline calibration pipeline affected see ITDM

EEE:

  • OCD call on rack 2.01 which was powered down. After fuse repaired

VAC:

  • see above ...

XPD:

  • Rack 2.01 --> Camera of SR imagare is not working
    • situation not clear, being investigated --> IP conflict?
    • Janusz suggests to powercycle the camera

DET:

  • many to report

ITDM:

  • 10:00 maxfell gpfs update

XRO:

  • SA2 mirror calibration

LAS:

  • remainder change of set point for SCS to 112 kHz

UNSYS: 

  • nothing to report

SPB/SFX:

  • nothing to report

FXE:

  • preparing for user experiments
    • concerned about optical sync of PP Laser, probelm of last week was fixed but no reason found
    • test last thursday optical sync lost again while moving optical delay stage
    • FXE

MID:

  • alignment of optical laser alignment in joined hutch.
    • please

HED:

  • nothing to report

SCS:

  • nothing to report
    •  

SQS:

  • last week Thursday night
    • mono drift investigated --> preliminary analyisis points to the grating as the drifting component