Message ID: 307     Entry time: 09 Mar 2022, 10:15
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 09.03.2022 
General Announcement:
-	 

CTRL:
- Nothing major to report.

DA:
- Nothing to report.

EEE:
- Supporting instruments.
- Replacement uTCA in HED optics crate on Monday was done; being monitored during next two weeks.

VAC:
- Issue with SA3 broken ion pump controller in SA3; ZZ was done to replace controller.
- Issues when entering tunnel: XD2/4 PC turnstile crashed and D3had to reset software. Caused 30-min delay in entering tunnel.

XPD:
- Issue with FXE for XGM in their hutch: electronics did not work but was taking care by Theo / Fini. FXE has to confirm if this is fine now.

DET:
- Nothing to report.

ITDM: 
- Intervention on Monday accordingly to the plan with reboot of 2 servers at SA1/FXE. Maybe another server to change in later date.
- Influx database issue on Monday: all data until 22:30 in the evening are not reliable (SA1 and SA3). Mid-term plan with CTRL to split SA1/SA3. Under investigation to find the cause.

XRO:
- FXE stability issue: last night beam was stable after the ZZ was done to switch off cooling systems of mirrors and clean tent.

LAS:
- 3 PP-lasers in operations: working
- Max L. asks for news on the winter maintenance 8D report. 
- LAS send a ticket with TS concerning connection of front end UPS. Needs follow up.
- Announcement by TS on Saturday 25th June: concerning to LAS - what are the consequences? Max L. needs feedback to plan next summer maintenance period. 
Tobias Clever says it is connected to construction of office building; needing new transformators and concerns power supply and not 35degrees water. XO will help with feedback.

UNSYS:
- SA1 PSs problems seemed to be solved at Desy side (new gap program done by Lars).
- Error signal from ambient field coils in cell14/SA1: Fixed by Suren A.
- In SA3 a problem with stuck quad mover: fixed by Suren A. with workaround;
- Cell 11 / SA3 phase shifter motor: could be another damaged device. It needs ZZ access.

SPB:
- Nothing to report.

FXE:
- Feedback on the XGM will be discussed internally.
- Beam jitter observed yesterday; thanks to all efforts.
- Energy change this morning took longtime.

MID:
- Monday afternoon: Karabo issue with control room due to broker pile-up; all fine now.
- No issues with HXRSS; used beam yesterday.

HED:
- Continuing prep for next week; also investigation on shielding.

SCS:
- Preparation for Liquid jet.

SQS:
- Nothing to report.