SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 102
Entry time: 16 Mar 2020, 09:36
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes Dipatch Meeting March 16th, 2020 |
|
|
FXE:
- Beamline is in safe state;
- Minor Jungfrau calibration issues over last week. In touch with DET and EEE;
SPB:
- Good exercise: experiment run with only 2 users. Successful beamtime with data taken: to be analysed by users;
MID:
- Successful beamtime with good beam conditions and data has been taken;
- Beamline is in safe state and most of staff is in telecommuting;
EEE:
- Start collecting a list of broad activities to take place in case of a long shutdown;
- No major issues to be fixed;
CTRL:
- Few cameras and detectors hiccups – e.g. DAQ re-start bring system back;
- Most of people will run from home office / telecommuting;
- Tests together with EEE/FXE still to be performed this week - to be scheduled;
DET:
- DET is placing a plan to warmed up detectors and be ready for shutdown;
- AGIPD, DSSC are already in safe mode; |