Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 391
Entry time: 01 Feb 2023, 10:56
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 01.02.2023 |
|
|
General Announcement:
- A. Galler reminds instruments to use the Operation-2023 e-log for daily reports.
CTRL:
- Issue with Karabo dataloggers connection to newly available Proxies (not connecting). Problem is understood and a fix in under made. Then one shall apply to topics (takes 5-10 minutes downtime).
DA:
- Nothing to report.
EEE:
- Nothing major to report; working on a received ticket.
VAC:
- Last night FXE reported issues with SA1 ion pump. Vacuum was OK but the status of Karabo was wrong. It's under further investigation and Wajid E. comments a ticket was sent and is being addressed.
XPD:
- Nothing to report.
DET:
- Detector installed back to HED (ePix) after successfully intervention.
ITDM:
- Updates of Maxwell cluster was done yesterday. If something unexpected happens please get back to ITDM.
XRO:
- Instruments taking beam at hutches and no major problems have seen so far.
LAS:
- SA1 and SA2 PPL's are in operation.
- SA3 PP-laser is under preparation.
UNSYS:
- Issue with cell24/SA1 undulator motion happened and was fixed on Monday.
- Gap of exchanged undulator in SA2 seems not be correct and it is needed a ZZ for the gap calibration, possibly next Monday (tbc).
SPB:
- Camera devices goes to error and needs power cycle.
- After power cut some motor lost positions.
FXE:
- He gas supply: A. Galler informs that currently there is no shortage of He for the next two weeks.
MID:
- Making good progress by setting things up at instrument.
- One sample stage has problems and EEE will work on Friday.
HED:
- Preparing for taking beam on Friday and currently working on Dipole laser.
SCS:
- Problem with new Interlock and BKR had to overwrite it. Beam is now at the instrument.
SQS:
- Not present. |