  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 97     Entry time: 10 Feb 2020, 10:12
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes Dispatch meeting Feb 10th, 2020 
SPB:	Nothing to report;

FXE: 	Everything ongoing; nothing special to be reported;

MID:    Finalize motors of split and delay line; MID has to test interlock for vacuum loop update.

HED:	Commissioning of laser heat table. It may need assistance from EEE and CTRL during the week.

SCS:	Nothing to report - Last week's mounted setup will be disassembled in order to mount the standard setup for users;

EEE: 	OCD was called from XRO during beamline alignment of SA2: 1 BMPI motor had a problem and is under investigation - EEE reminds on the new homing position for 
negative direction motion.

CTRL: 	Following reset of train-ID and timing system for today.

XPD: 	Shifted Beam Pointing Studies from A. Koch to Tuesday. 

DET: 	Nothing to report

*machine is currently not running due to filter clean in the cold compressor. Shall be re-started this afternoon and by tomorrow must be lasing.
*Master time reset and train-ID reset this morning. Then EEE (check systems), followed by CTRL (karabo servers re-start) and ITDM (check DAQ operation). LAS and DET are 
informed.
*Wednesday: Network stress test with Cameras by CTRL on Wednesday 12:00-14:30.