Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 24     Entry time: 27 Mar 2019, 10:48
Author: Adriano Violante 
Location: General 
Severity: Information 
Subject: Minutes of the Technical integration meeting 27.03.19  

SPB/SFX

  • CRL implementation in the hutch will happen in April. AE and EET involved. ==> Connectors on the beckhoff frames need to be re-shuffled according to the newest version of the EPLAN documentation. EET will take care of that, so that the loop can be started as soon as possible.
  • CSS crate is ready. Loop 7 bridged (same loop as CRL). Test can start tomorrow.
  • AGIPD motion. Prelminary tests are being performed to be ready for the final tests in the march shutdown. ==> Some issues with cabling of limit switches were found. SPB will fix it today/tomorrow. ==> Test starting today. From the Karabo side seems ok.
  • AGIPD chiller has been shipper for repair. SPB/SFX are trying to find alternative solutions for the next users run.

FXE

  • 4 cables are needed to control some stages and were requested to AE/EET. After checking  by NC some rewiring from FXE side on the module side is needed to make the electronic solution proposed usable. NC is in contact wit TKorsh.

SQS

  • Loop 8 and 11 HW will be prepared by AE this week and can run by next week.
  • Interlock updates ongoing
  • Meeting organized by PGessler to review the recurring issues with the digitizers

SCS

  • When operating the machine in the train pattern (not  10 Hz) mode and pulse on demand mode the data from the XGMs in XTD10 and SCS is not recorded. ==> That's still the case and it is caused by a Doocs update not agreed with CAS. ==> Ongoing. ==> Meeting took place yesterday. Issue seeems to be closed.
  • The dangling cable of the sliding door has to be fixed. This is supposed to be done by ARathjen during the March shutdown.
  • A Change in the storage of raw data of the XGM is required. SCS is discussing with XPD (Theo). Later ITDM and CAS will be also involved.
  • Loop 13 being prepared. As well as 11. Interlock updates ongoing.

MID

  • Smaract stages do not work propery and reliably. High priority. Has to be clarified with AE since it is not clear whether this is the same issue that SCS had and for whoch they developed a workaround. ==> BB will contact the Smaract company to address the issue.
  • Loop 9 has been updated and the broncos can now be controlled.

HED

  • Cables and loops for HED instrumentation. LW is monitoring closely the installation of cables to give the go ahead to AE for the starting of tyhe loops. Loop 5 is still the priority. High priority cables for Loops 5, 7,8 should be all installed by the end of this week.

 

OPT Lasers

  • Modules for the time stamp have to be installed by AE. How long does it take? Will be discussed offiline with PG. ==> Installation dates: SASE1 in summer shutdown,  SASE3 being worked out, SASE2 will follow. Workaround with time stamp is being investigated. ==> PLCs have to be updated. HW ready.==> SASE3 OK. SASE2 crates being changed now.

XRO

XPD

  • Hirex 2 will be shipped from Cologne tomorrow and will be brought into the VAC lab. Crates ready, cables ready. AE can support local tests outside the shutdown week.==> Hirex will be installed in the shutdown and probably a couple of testt will need support from AE. These can be scheduled for the 01/02.04. Vac loop is affected.==> AE only supporting crates installation and powering.

 

VAC

DET

  • 3rd branch SA3 - one ion pump has to be included in the VAC loop (update tomorrow)

AE

  • Timing update foressen for today will rpobably happen a little bit later than expected in SASE2.
  • Waiting for the finalization of the MID LDM risk assessment from SRP to allow the usage of the remote control of the device.

​​ITDM

EET

CAS

SRP

TS

AoB