Group Selection Page HELP Controls Group Data Analysis Group ITDM WP76 DET Vacuum EEE WP78 FXE SPB HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 27 of 32  Not logged in ELOG logo
Entry   notes Dipatch Meeting April 6th, 2020, posted by Frederik Wolff-Fabris on 06 Apr 2020, 09:50 
CTRL:
- It was remotely observed that some cameras were consuming too much memory. By remotely re-starting these devices the issue was solved.  
- No calls to the OCD during the weekend.
Entry   Technical Integration Meeting 01.04.2020, posted by Andreas Galler on 01 Apr 2020, 09:19 


CTRL:


productive meeting with HED

CTRL will ask the other instruments if a similar concept could be agreed upon


discussion
Entry   , posted by Andreas Galler on 30 Mar 2020, 08:57 
CTRL:


Broker Pile Up in 4 topics over the weekend

LAS affected in all topics, LA2 even twice
SPB affected once


mitigation
startegy worked


EEE:
Entry   Technical Integration Meeting 25.03.2020, posted by Andreas Galler on 25 Mar 2020, 09:32 
Currently EuXFEL enforces a hand-off policy for instrument/tunnel hardware. That includes remote control of motors, pumps,
etc.. as well as changing config files. If and when this policy is lifted will be communicated during Dispatch and Technical Integration Meetings. Please
also don't hesitate and contact XO in case of any questions.
Entry   notes Dispatch meeting Mar 23 2020, posted by Andreas Galler on 23 Mar 2020, 08:57 
Currently EuXFEL enforces a hand-off policy for instrument/tunnel hardware. That includes remote control of motors, pumps,
etc.. as well as changing config Files. If and when this policy is lifted will be communicated during Dispatch and Technical Integration Meetings. Please
also don't hesitate and contact XO in case of any questions.
Entry   Technical Integration Meeting 18.03.2020, posted by Andreas Galler on 18 Mar 2020, 09:26 


SPB:


interument parked
power cut --> someon needs to come in
NJ: what'S that status of the VAC
KC
Entry   Notes Dipatch Meeting March 16th, 2020 , posted by Frederik Wolff-Fabris on 16 Mar 2020, 09:36 
FXE:
- Beamline is in safe state;
- Minor Jungfrau calibration issues over last week. In touch with DET and EEE;
Entry   notes Dipatch Meeting March 9th, 2020, posted by Frederik Wolff-Fabris on 10 Mar 2020, 12:44 
* Users are scheduled to be here this week (4 beamlines in user runs). SPB, HED, MID report several users have cancelled the travel. Beamlines are making
mitigation plans 
to run experiments.
Entry   notes Dispatch meeting Mar 2 2020, posted by Andreas Galler on 04 Mar 2020, 08:49 
SPB:


AGIPD improvement campaign great success
EEE --> 2nd C&C worked just fine


FXE:


BTM tests successful
Johann MDL motors should be in closed loop
JF CTRL device crashed


MID:
Entry   notes Dispatch meeting Feb 24 2020, posted by Andreas Galler on 26 Feb 2020, 09:06 
SPB:


nothing to report


FXE:


not present due to group retreat


MID:
Entry   notes Dipatch Meeting Feb. 17th, 2020, posted by Frederik Wolff-Fabris on 17 Feb 2020, 12:02 
FXE:
Nothing to report: no issues;
Entry   Notes Dispatch meeting Feb 10th, 2020, posted by Frederik Wolff-Fabris on 10 Feb 2020, 10:12 
SPB: Nothing to report;

FXE:  Everything ongoing; nothing special to be reported;
Entry   notes Dispatch meeting Jan 20 2020, posted by Andreas Galler on 22 Jan 2020, 09:16 


SPB:


nothing to report


FXE:
Entry   notes Dispatch meeting Jan 13 2020, posted by Andreas Galler on 15 Jan 2020, 09:09 


SPB:


Testing coordinated movement of Mirror motors with the MC2 lib on lemo drives
optics hutch vented accidentally vented but
Entry   Report of the Technical integration meeting , posted by Adriano Violante on 08 Jan 2020, 12:36 
SPB:


Coordinatd motion for MC2 motors is going to be rolled out by EEE soon.


FXE:


No issues to report.


MID:
Entry   Report after tech. Int. meeting 09.30, posted by Adriano Violante on 18 Dec 2019, 10:06 
MID:


SDL tests ongoing. Important motors have been tested. Alignment of the mechanics with the alignment laser ongoing. Will be pumped over
Christmas.


 EEE:
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 16 Dec 2019, 09:28 
FXE:


uTCA update has been completed by EEE on Friday evening. Information will be passed to controls for the finalization.


SCS


The interlock system for the big sliding door has to be fixed. JTD is following up the issue with TS and SRP.
MT will talk
Entry   Report after Tech. Int. meeting 09.30 , posted by Adriano Violante on 11 Dec 2019, 09:54 
FXE:


New optical table will be installed today. Access to the hutch could be limited.
The new Airbox installed by D3 is colliding
with the sliding door. It might be problematic to bring the new laser table in. SRP informed. It is being followed up. 
uTCA update will
Entry   Report after dispatch meeting 09.00, posted by Adriano Violante on 09 Dec 2019, 09:22 
FXE:


No major issues.
Karabo will be updated to the version 2.7.0. on Friday.
uTCA update will be done on Thursday.


SCS:


it was forgotten to involve EEE in the PLC update of the train picker in the tunnel. Now the issue is solved.


MID:
Entry   Summary of the technical integration meeting, posted by Adriano Violante on 04 Dec 2019, 14:18 
FXE


No major issues - PLCs update has been started by EEE (BB)


SCS


Hrixs and related components will be delivered on 13 and 14.01.2020. SCS is coordinating the works with TS in order to crane the chambers
ELOG V3.1.4-7c3fd00