Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 26 of 26  Not logged in ELOG logo
ID Date Author Location Severity Subject Text Attachments
  11   22 Feb 2019, 12:36 Adriano ViolanteGeneralInformationMInutes of the dispatch meeting 09.00SPB/SFX


Pulse picker commissiong
- Issues concerning motors position and triggers
  
  10   20 Feb 2019, 11:16 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 20.02.19 SPB/SFX


CSS component commissioning.
Concept and implementation being finalized.==>
  
  9   18 Feb 2019, 10:09 Adriano ViolanteGeneralInformationMinutes of the dispatch meeting 09.30SPB/SFX


Data aggregators were often
crashing during the WE and needed to be re
  
  8   15 Feb 2019, 12:14 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


SPB requires the new trigger
solution to be implemented for AGIPD. This
  
  7   13 Feb 2019, 10:59 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 13.02.19 SPB/SFX


CSS component commissioning.
RBean is discussing with AE. Concept and
  
  6   11 Feb 2019, 09:59 Adriano ViolanteGeneralInformationMInutes of the dispatch meeting 09.30SPB/SFX


Beam is back on Wed. night.
IT
cables in D.23 were re-measured on friday.
  
  5   08 Feb 2019, 10:42 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


IT cables in D.23 were
re-measured yesterday. Waiting for the measurements.
  
  4   06 Feb 2019, 11:13 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 06.02.19 SPB/SFX


AGIPD commissioning and
tests. ==> intervention on the wings is
  
  3   04 Feb 2019, 10:17 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.30SPB/SFX


Waiting for the loop 12
to be running to start the commissioning
  
  2   01 Feb 2019, 12:49 Adriano ViolanteGeneralInformationReport after dispatch meeting 09.00SPB/SFX


Open AGIPD wing. Next 3
days are needed for fixing purposes.


FXE
  
  1   30 Jan 2019, 11:26 Adriano ViolanteGeneralInformationMinutes of the Technical integration meeting 30.01.19 SPB/SFX


Planned for the next 2
weeks

AGIPD commissioning and
  