General Announcement:
- The Photon Run Coordinator will re-start next Friday July 3rd. Please also feel free to contact him/her (9-4800) for daily coordination and communication with the 
machine/BKR. 
- Interlock / TUV tests are ongoing in tunnels. Next Wednesday it starts in the experimental Hall / SASE instruments.

CTRL:
- CTRL has a plan to switch the Data Loggers on Wednesday. This will cause a downtime on this service for about 5 minutes. A follow up will be announced afterwards.

DA:
- Not present.

EEE:
- EEE has made an agreement with HED on the cabling issues. 

VAC:
- Tunnels are closed: maybe next week after Interlock tests the XTD6 and XTD9 tunnels will be open for a couple of days.
- If access in tunnels are needed (not only XTD6 and XTD9), please make a request by filling the table at the Desy/BKR elogbook 
(https://ttfinfo.desy.de/XFELelog/index.jsp), located under "Access Requests".

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- All lasers are fine.

UNSYS: 
- Nothing to report.

SPB:
- It has tested the new Karabo for the Jungfrau detector and result is OK.
- This week SPB plans to test cameras.

FXE:
- Nothing to add.

MID:
- All fine.

HED:
- All fine.

SCS:
- Not present.

SQS:
- Nothing to report.