Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 147
Entry time: 29 Jul 2020, 08:59
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 29.07.2020 |
|
|
General Announcement:
CTRL:
- INfluxDB migration is running smoothly, tomorrow the last topics will be switched to influx only
- some Basler / Andor cameras not working at 10 Hz is related to the data network --> depends
DA:
EEE:
- Company Wille is on-site for hardware installations
- hRIXS,
- HED cable installations
-
VAC:
XPD:
DET:
- commissioning shifts with AGIPD
- pn CCD at SQS also on commissioning
ITDM:
- issue from Monday wrt crippled DAQ when having no sow data in a datasource
- the fix reported on Monday only works partially --> earliest estimate for fixing is now next week
-
XRO:
LAS:
UNSYS:
SPB:
- OCD for Basler cameras
- OCD for MC2 stages (problem with encoders, EEE is informed)
FXE:
- Major issue with the machine wrt to big brother
- JUngFRAU seems to be more affected by the DAQ glitch
- GOTTHARD detector should be re-integrated into the DAQ
- K. Wrona clarifies that only a reconfig of datasources is needed
MID:
- beam looks unstable
- horizontal jitter is higher than usual
HED:
SCS:
- no issues
- Daniele: is the soft-mono solved?
- TM comments: the pre mirror is in place piezos are working
SQS:
- no issues
- pnCCD commissioning
|