208
|
17 Mar 2021, 09:15 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 17.03.2021 | General Announcement:
- nothing.
CTRL:
- LAS reported the pulse statistics did not work properly: re-started systems due to lost connections.
- OCD call related to HED AGIPD test system: fix ongoing.
- Update on train-ID slow data on XGM: CTRL is in touch with Desy and Theo. Question to SPB and XPD: how much effort is needed for that CTRL and ITDM to place the missing information in the run. Involved parts will discuss an agreement by the end of the week. Steffen H. will prepare a summary to inform XPD.
DA:
- no important news.
EEE:
- no important news.
VAC:
- nothing to report.
XPD:
- nothing to report.
DET:
- nothing special.
ITDM:
- all fine.
XRO:
- Not present.
LAS:
Going fine: Laser pattern issue from yesterday was solved by CTRL.
UNSYS:
- Problem on Monday with quad mover cell18/SA1 took 6 hours on ZZ. It is now fixed.
- A problem with undulator segment on cell36/SA1 needs diagnostic and eventual ZZ access. RCs are contacted.
SPB:
- The samples to be used next week are challenging to prepare.
FXE:
- Used beam yesterday. No problems to report.
MID:
- all fine.
HED:
- nothing to report.
SCS:
- nothing to report.
SQS:
- all good. |
224
|
12 May 2021, 09:21 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 12.05.2021 | General Announcement:
- User Operations Meeting takes place on next Friday 09:00.
CTRL:
- CTRL would like to excuse itself to people receiving an automatic SMS tonight for notification. This was a test message and now it’s turned OFF (Good side: test for lasers went well).
- ADQ digitizers: two fixes are driven and based for SQS commissioning. CTRL encourage instruments to get in touch with contacts for making the update for the last version.
DA:
- Follow up from Monday / calibration update (on behalf of cal team): it worked as planned. AGIPD seems to run faster now.
- For SQS Remi detectors/digitizers can also be used.
EEE:
- nothing to report
VAC:
- nothing to report
XPD:
- are preparing for FD studies next week
DET:
- Follow-up on LPD online calibration pipeline pointed last Monday’s meeting: work is on progress and is expected to be ready for next week.
- DAQ processing for AGIPD: a minor bug in validation is reported and under investigation. But it is currently working.
- Issue reported for SPB for data aggregators: follow up with CTRL.
ITDM:
- nothing to report
XRO:
- nothing to report
LAS:
- nothing to report
UNSYS:
- nothing to report
SPB:
- not present
FXE:
- Thank to DET and DA for pipeline calibration. Initially it looks promising.
- Last week: digitizer went to wrong configuration. To be fixed with new updated.
- FXE will use the beam during the nights. D. Khakhulin will inform PRC and XO via e-mail.
MID:
- all fine
HED:
- not present
SCS:
- nothing to report
SQS:
- nothing to add |
234
|
16 Jun 2021, 08:37 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 16.06.2021 | General Announcement:
- Interlock test next 2 weeks starting on monday - from next wednesday the photon tunnels will be closed; Tests are the XHEXP1 take place on 30.06, 01.07 and 02.07 with the last date as reserve; An email is going to be send by FWF to the xo-info@xfel.eu list.
CTRL:
- List of items to be sent to readiness: 1. problems with lima based cameras (Lima library does not work – needs to be updated: instruments contacts shall get in touch); 2. In SA1 there is legacy Undulator Karabo scenes – vector properties have to be adapted; 3. Counter Clocking motor devices upgraded next week.
- A. Koch asks if SA1 was working this morning. Steffen H. says there were updates but must be running now.
DA:
- Next wednesday will be the Offline calibration update deployment
EEE:
- Shutdown activities going well; "Wille" is short in people but scheduling adjustments with FXE and MID is organized.
- If there are short circuits or mal functions in the Beckhoff crates and current is not high enough to trigger the fuse it may be a fire risk. Solution is developed without impact in firmware, just a replacement of fuses. EEE starts today at SPB the changes; Based on this experience a plan will be made for the other systems and EEE will get in touch with groups.
VAC:
- try to get the works finished in the tunnels
- waiting for the Beckhoff crate works
XPD:
- Most of the tunnels works have been done; others are ongoing; No surprises are expected.
- MKK logbook from Desy reporting about electrical issue. XO will check. (XO update at 13:30: automatic mailing system is being commissioned and under testig; no power failure happened at the time).
DET:
- Work with DSSC in SQS going as planned.
ITDM:
- Work currently being done at FXE.
- Reminder of Friday afternoon gateway update.
XRO:
- Not present.
LAS:
- Nothing special to report.
UNSYS:
- Greasing the linear stages for undulators but not in SA2 (missing grease).
- SA1/SA2 after middle plane alignment UNSYS redefined the minimum gap and will be communicated through XO.
- Cell#36/SA2 there is a cable disconnected that need to be fixed.
- SA1/SA2 working with PS tables for extending operating tables for higher photon energies.
SPB:
- Work with EEE changing all the crates (Beckhoff)
FXE:
- Nothing to add
MID:
- Several ongoing infrastructure works are going fine.
- Worried with Beckhoff fuses (reported two years ago by Konstantin). It will be good to hear experience with SPB.
HED:
- Nothing to add
SCS:
- Nothing to add
SQS:
- Nothing to add |
245
|
26 Jul 2021, 09:20 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 26.07.2021 | General Announcement:
- Power glitch 3 times at night, what brought down the beam for 1,5 hour each time. Please report to XO if you find devices affected.
CTRL:
- Datalogger update to take place today between 16:00-17:00. Please inform CTRL in case of problems with this schedule.
- Aravis camera and bunch pattern decoder to be updated at around 14:30. Please inform CTRL in case of problems with this schedule.
DA:
- OCD side: no new problems.
- Follow up last Wednesday: better is to use the new Karabo with the fix and not to downgrade the Karabo version.
EEE:
- Ticket from SCS was solved.
VAC:
- Some trouble with the pumps in the gas attenuator SA3. It needs to be fixed today in the tunnel with a ZZ (30 mins).
ME.
- Not present.
XPD:
- Are investigating, if something is affected by the power glitch. So far nothing was found.
DET:
- Nothing to report.
ITDM:
- Two issues to follow with MID: 1. Bassler camera seems to be the data wrongly recorded at DQA. Tests need to be done; it’s a camera used for feedback. Ulrike B. will talk offline with K. Wrona.
- Second issue: on Friday there was one ADC from tunnels to be used from MID was requested a bit late. Data comes from the uTCA from Desy network. If this device is going to be used in full, it has to be set inside Desy network.
XRO:
- Not present.
LAS:
- Two incidents: the power glitch at 19:23 yesterday took Amphos in SA1 down. It is back and operational; In SA3 LAS is further investigating the Amphos.
UNSYS:
- No problem with the power glitch.
- The temperature in SA3 Undulators is stable.
SPB:
- SPB imager at XTD9: is not working and has to be changed the outcome needs to be fixed of XPD. Naresh K. will contact SPB.
FXE:
- Not present.
MID:
- All good at MID – not heard on affected systems due to the power glitch.
- Friday afternoon confusion with the fix of Extra Foam bridge. Probably DA is aware.
HED:
- Vacuum system ok after power glitches.
- Nothing to report.
SCS:
- Not present.
SQS:
- Not affected by the power glitch. |
246
|
28 Jul 2021, 09:29 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 28.07.2021 | General Announcement:
- No general announcement.
CTRL:
- Problem with cameras / DAQ: fixed yesterday and tested at SA2/MID.
- Issues with SA3 vacuum loop: work ongoing and further investigations are needed.
DA:
- Nothing to report.
EEE:
- Cables available for HED to be installed next week – date to be discussed offline.
- Fast electronics side: working on FXE and HED issues;
- Nerea J. reports on the VAC/SA3 issues: instability with devices going into an unknown state. Alessandro S. works at the night shift in the DOC and will try to fix a permanent fix during the night.
VAC:
- SA3 issues are affecting also the gas attenuator (not only general SA3 vacuum loop but also GATT is affected, which has its own loop). There are no physical events - seems to be electronic. Stability issues to connect devices; Seems to be more related to infrastructure (PLCs). Further investigations are needed.
ME:
- Not present.
XPD:
- SPB imager: change setting of motors (it shall work now) and next week when A. Koch is back further investigations will be done.
DET:
- During the night after 02:00AM: SPB AGIPD K-bridge went OFF. Under investigation. Detector recovered this morning.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Nothing special to report.
UNSYS:
- Nothing to report.
SPB:
- Issues with wings of Agipd, causing also interlock trigger. Under investigation.
- 11PM last night: laser interlock triggered. It happened also in the past and SPB will get in touch with Safety today.
- XTD9 IMG: currently working but a permanent fix is welcome in the future.
FXE:
- Not present.
MID:
- All fine.
HED:
- Major issues with Agipd detector yesterday (thanks to DOC for help): 1. Could not kill the service and CTRL investigated; 2. Clock and control did not work (it has worked at CFEL last week). The issue was solved by changing the clock controller back to old configuration (EEE helped). Bruno F. comments that the clock control had to be downgraded in this detector (it worked in other detectors, only this one did not work). Further investigations will follow.
SCS:
- Change of speed from the monochromator was not possible. EEE and CTRL are working on it.
- Next week will run with a special train picker / bunch sequence pattern as the one used last week.
SQS:
- Vacuum problem as mentioned.
- Commissioning DSSC for future beamtimes. |
87
|
27 Nov 2019, 09:25 |
Andreas Galler | General | Information | dispatch meeting Mon Nov 25 2019 | FXE: no issues
SPB: no issues
MID: Split & Delay line arriving on Friday, MID aims for a quick integration into instrument / beamline
EEE informed to switch Hexapod motors from loop3 to loop 7
HED: changing loop1 (JJ X-ray motors) from open to closed loop operation
SQS: KB works, see sometimes spontaneous switching of end switch logics
EEE: MID, SPB, VAC loop updates running this week;
no triggers for experiments available until end of power off work
Jörn: cabling for MID is in full swing, for future installations first check phase 1 cabling, for non blocking
HED: cabling
SCS company Witte 30 ccables
FXE: two CRDs not approved yet, no cabling during this shutdown
Controls:
|
88
|
28 Nov 2019, 15:42 |
Andreas Galler | General | Problem | affected ITDM Systems after power cut tonight |
XHQ.E1.092
SW-HH-AL-271 was available
SW-HH-AL-272 came back after the DL switch was back (see below, ca 09:33)
SW-HH-AL-273 had to be power cycled and rebooted by NOC through console to come back fully (ca. 10:52).
SASE1 balcony room 38
restarted at 4am:
DELL servers:
exflprx03n0
exflprx04n0
exflprx112
exflpcl01n0 to 08n0
exflpcl18n0
SuperMicro servers:
exflonc09 to 12 (4-in-1 chassis)
exflong06
IBM ESS systems stayed off, as well as storage jbods
exfl-ons-gs111 and 112
exfl-ons-gl111 and 112
exfl-ons-gl113 and 114
IBM server (hosting ems servers for OS installations) was off as well
exflkvm01
SuperMicro servers stayed off:
exflong03 to 05
juniper (management network) switch stuck at booting, power cycled, after long time finally came back, but we were lacking management network over whole site
SW-HH-AL-DL-07 (office network distribution layer) switch was stuck at booting, came back after power cycling. Some (not all) office switches were not available because of this, seemingly the failover between AL and DL didn't work. Both this switch and the (permanently available) ...DL-08 were correctly cabled to separate PDUs.
Second fuse in BR38 rack 7 was out and had to be pushed back in manually (made power redundant again).
SA1 tunnel:
exflcon08n0 restarted at 4am, but apparently switch in the tunnel was off till 10:30 and since that time the server was accessible
E0.604
All systems were affected. We need the clear statement from YS why the second line did not work.
DELL servers rebooted at 4am:
exflprx01n0
exflprx02n0
exflpcl51n0
exflpcl52n0
exflpcl53n0
exflcon03n0
exflcon04n0
exflcon05n0
exflcon150
exflcon153
exflcon156
exflcon157
exflons01 and 02
exfldaq01 and 02 (gitlab CIs)
exflst105 (karabo project db - development and labs)
IBM servers stayed off:
exflpcl54n0
exflpcl55n0
exflpcl56n0
exflpcl57n0
exflonc41
exflonc41
IBM ESS system stayed off:
exfl-ons-gs901 and 902
There are also several servers (proxmox, serving VM OnlyOffice) all rebooted at 4am
List of h/w failures:
exflpcl05 PSU dead
exflong04 and 05 PSU dead (in exflong04 was actually since yesterday after reboot for OS updates)
may not be related to power glitch
exflprx106 RAM DIMM error
Intel server:
exflonc21 to 24 (4-in-1 chassis) PSU dead
|
95
|
15 Jan 2020, 09:09 |
Andreas Galler | General | Information | notes Dispatch meeting Jan 13 2020 |
SPB:
- Testing coordinated movement of Mirror motors with the MC2 lib on lemo drives
- optics hutch vented accidentally vented but root cause is understood and vacuum had been reestablished
FXE:
- XTD2 CRLs have encoder problems --> cables damaged --> repair strategy is being evaluated with EEE
MID:
- SDL should enter the hutch by the end of January
SCS:
- pulse (train) picker to be installed in the tunnel by the end of this week
EEE:
- FXE had been migrated to MC2 lib
- motors need to be recalibrated
- XTD6 motion part is to be migrated to MC2 lib
- SQS gets interlock updates
CTRL:
- busy with tunnel, additional support for XPD (imagers motion components)
|
96
|
22 Jan 2020, 09:16 |
Andreas Galler | General | Information | notes Dispatch meeting Jan 20 2020 |
SPB:
FXE:
- MC2 library motor commissioning on-going
MID:
- SDL motor parameters defined, however one crate is blocked by Wille and 6 motor connectors (Harting material) are still missing
once fixed, motor paramaters can be uploaded
- WCB (wall connection boxes) in otics hutch are partially finished
HED:
- Wille is working on some crates and the respective Beckhoff loops are down for the moment
- loop updates from Tuesday on
EEE:
- additional limit switched for XTD6 CRLs (MID) are being installed
- HED is asking for limit switches on their XTD6 CRLs as well --> EEE and HED will investigate when and how
- cable change in FXE starts this week with exchaging wrongly poled SHV cables
CTRL:
VAC:
XRO:
|
99
|
26 Feb 2020, 09:06 |
Andreas Galler | General | Information | notes Dispatch meeting Feb 24 2020 | SPB:
FXE:
- not present due to group retreat
MID:
- Mono done, no severe issues from commissioning weekend
SCS:
EEE:
- SQS pnCCD cables have been installed, waiting for crate to connect
CTRL:
- two minor OCD call and one regarding AGIPD
- SPB not aware that no support was scheduled for AGIPD
XRO:
- piezo karabo device and firmware in HED mono need to be checked for compatibility
ITDM:
- 2 calls
- derver down and restarted
- data aggregator down and restarted
- new RunConfig delpoyed at FXE
DA:
- jupyterhub @SCS showing performance issues --> investigated by DA
|
100
|
04 Mar 2020, 08:49 |
Andreas Galler | General | Information | notes Dispatch meeting Mar 2 2020 | SPB:
- AGIPD improvement campaign great success
- EEE --> 2nd C&C worked just fine
FXE:
- BTM tests successful
- Johann MDL motors should be in closed loop
- JF CTRL device crashed
MID:
- AGIPD Flat Fields done
- Data Correction pipeline was down --> 1 day lost
- PPLaser comm this week
- extrafoam issues
SCS:
EEE:
- updates for SDL (MID)
- fastADC issue --> don't take more than 40k samples; bugfix in progress
CTRL:
- 8 OCD events
- mostly deployment isues
- FXE DA3 overload
- old version of scantool @ SCS
XPD:
- unusual behaviour of beam pos measured with XGM
- cross check done yesterday
ITDM:
- DA crashes --> being investigated
HED:
- tecnosoft terminal issue
- motor ran into Ty limit (CCW) and got stuck due to tecnosoft logic
|
103
|
18 Mar 2020, 09:26 |
Andreas Galler | General | Information | Technical Integration Meeting 18.03.2020 |
SPB:
- interument parked
- power cut --> someon needs to come in
- NJ: what'S that status of the VAC
- KC & RB: safe state, roughing system still running, in the event of a power cut this needs to be looked at
FXE:
- nothing to report
- NJ: VAC in safe state? --> MK yes everything is switched off
MID:
- instrument parked, VAC is running but pumps will be stopped today and partially vented
- gate valves are closed hopefully the VAC stays
SCS:
- SCS in safe state, all pumps running
- valves around KB are permenantly closed
- in the event of a power cut all other gate valves will close
- loop update done yesterday
EEE:
- preparation for safe state ongoing
CTRL:
- is master timing going away or not?
- if master timing goes down, some devices
- ICI contacts identify what can be remotely done and what not
ITDM:
HED:
- HED is going to sleep within the next two days
DA:
- focus on long standing tasks
XRO:
- beam transport is going to be parked today
|
104
|
23 Mar 2020, 08:57 |
Andreas Galler | General | Information | notes Dispatch meeting Mar 23 2020 | Currently EuXFEL enforces a hand-off policy for instrument/tunnel hardware. That includes remote control of motors, pumps, etc.. as well as changing config Files. If and when this policy is lifted will be communicated during Dispatch and Technical Integration Meetings. Please also don't hesitate and contact XO in case of any questions.
SPB:
- reached safe state
- rougning pumps still runnning and valves open
- PLCs need to run for monitoring
FXE:
MID:
- absolutely safe
- cooling water connection
- PLCs switched off
SCS:
EEE:
- MID switched off completely, all other PLCs are running
- MID utca also shut down
- Jörn, plenty of time for additional planning
CTRL:
- broker logs ok from last weekend
- ICI contacts are in discussion instruments
ITDM:
- while instrument schutdown, network and servers are still running
HED:
- safe state, all motors switched off ( parameters saved) all valves close, ion pumps are stil running.
DA:
XRO:
- M1s parked on Friday, tunnel seems ok, lenses seem to be fine
- small problems in the GUI,
XPD:
- x-ray diagnostics had been secured last week, i.e. power ramped down. XGM vaccum needed.
FXE:
- Jungfrau chiller switched on, AMPHOS shutter chiller
- OGT3 no pump cart, ion pumps still running, gate valves closed
VAC:
- V0 closed, OCD looking at vacuum twice a day, PLCs needed and running
|
105
|
25 Mar 2020, 09:32 |
Andreas Galler | General | Information | Technical Integration Meeting 25.03.2020 | Currently EuXFEL enforces a hand-off policy for instrument/tunnel hardware. That includes remote control of motors, pumps, etc.. as well as changing config files. If and when this policy is lifted will be communicated during Dispatch and Technical Integration Meetings. Please also don't hesitate and contact XO in case of any questions.
SPB:
- instrument is fine in safe state.
- anyone having a VAC monitoring script connected to an SMS service?
- SH: comments that CTRL is working on that on a more general scope, but that needs a bit more time
FXE:
- JungFrau checked and powered down.
MID:
- everything is in a safe state.
- Martin D. reported a VAC issue --> gonna be clarified
- MD reports a spike in the VAC which might indicate a leak in a bellow
SCS:
- VAC interlock closed
- eplans for hRIXs electronics
- MT wrote a rudimentary webservice for monitoring karabo stuff via a webbrowser --> not to be used until sanctioned by CTRL
EEE:
- general remark: EEE provides two key systems: utca, and PLCs
- currently only PLCs for critical systems are covered by OCDs
- however all other PLCs are kept running, but not necessarily fixed on-site
- utca not critical --> thus no OCD for that
CTRL:
- all systems running
- limitations on karabo in the control network as stated in MB message --> finding out what that means for work on CTRL topics
ITDM:
- everything working, dropbox for urgently needed IT equipment available
HED:
- working on scenes / projects, recombining and cleaning up.
DA:
XRO:
- tunnel components secured, something on CRLs to be clarified with VAC
XPD:
VAC:
- VAC in tunnel is stable
- new software for vacuum pump carts developed and being rolled out
|
Draft
|
30 Mar 2020, 08:57 |
Andreas Galler | | | | CTRL:
- Broker Pile Up in 4 topics over the weekend
- LAS affected in all topics, LA2 even twice
- SPB affected once
- mitigation startegy worked
EEE:
VAC:
nothing to report
XPD
- vac systems in the lab had been secured --> secuvac valves installed plus webcams
DET:
ITDM:
- exflgateway hardware problem on Saturday --> fixed
XRO:
SPB:
- rough pump turned off, possibly lack of cooling water
- interlock tripped --> pressures raised
- were able to set remotely
FXE:
MID:
HED:
- VAC is fine, ion pumps are on, no roughing pumps running
DA:
|
107
|
01 Apr 2020, 09:19 |
Andreas Galler | General | Information | Technical Integration Meeting 01.04.2020 |
CTRL:
- productive meeting with HED
- CTRL will ask the other instruments if a similar concept could be agreed upon
- discussion with LAS this afternoon with respect to the current hardware policy
EEE:
- HED provided tasks that EEE shall do
- uTCA development ongoing
- review how digitizers are being used (fastADC, SPdevices, clock & Control)
VAC:
XPD:
DET:
ITDM:
- nothing to report, no indication of power glitch
XRO:
- no indication of power glitch
SPB:
FXE:
- nothing to report, problem to read out pressure values
- Bernd Baranasic: no ion pressure readings on OGT1
- in PLC it looks ok, but karabo shows 0
-
MID:
- meeting with DESY safety colleagues wrt PUMA, going to be bundled with LDM safety
- discussing with Bruno about digitizers
-
HED:
SCS
- only valves in loop1 were closed
- every few days a pump is failing, new behaviour
- JG: comments it is a known behaviour that one of the gauges showed an erratic behaviour (wrongly set epsilon in karabo)
- GM: answers, what happened on Saturday was slighty different
DA:
|
109
|
08 Apr 2020, 08:45 |
Andreas Galler | General | Information | Technical Integration Meeting 08.04.2020 |
CTRL:
- no bigger issues
- announcement: inital simulation environment ready which can simulate BECKHOFF devices
- shall be opened to all groups for karabo development
EEE:
- continue work
- shutdown task deadline may be too early
- if people have CRs CRDs, cable issues please submit
VAC:
XPD:
DET:
ITDM:
XRO:
SPB:
LAS
- waiting for karabo policy
FXE:
MID:
- nothing to report
- two weeks deadline extensions like EEE, DET
HED:
SCS
- shutdown list week extension
DA:
|
110
|
15 Apr 2020, 09:03 |
Andreas Galler | General | Information | Technical Integration Meeting 15.04.2020 |
CTRL:
- notificagion service device going to be tested this week
- ITDM: SMS part is operational but needs to be implemented
EEE:
- shutdown task list to be submitted today
VAC:
XPD:
- shutdown task list submitted
DET:
ITDM:
XRO:
SPB:
LAS
FXE:
MID:
- shutdown list
- Jörg and Jörn (EEE) align for shutdown task list
HED:
- aligning with Jörn (EEE) on shutdown taks
SCS
DA:
|
145
|
22 Jul 2020, 09:22 |
Andreas Galler | General | Information | XO integration meeting 22.07.2020 | General Announcement:
- Default beam positions are being implemented for each SASE at the FEL imager to reduce re-alignment offers for the instrumetns after shutdowns and facility development weeks
CTRL:
- minor OCD calls
- few MC2 motors not working -> target velocity was set to 0
- in SA1 the bunch pattern changes @10 Hz --> data logging system (with timers) gets overloaded ...
- if this was to become a normal mode of operation, the system would need to be adpated --> as for now bunch pattterns are not logged anymore
- remote user access to karabo
- soo to be tested with SQS
- inlfuxDB
- FXE 95% migrated, probably 100% at the end of the day
- LAS SA1 100% migrated
- MID, SCS shall reply when migration is possible (causes a short down time of datalogging)
- SPB, HED shall reply s.a.
DA:
EEE:
- issue with encoders in SPB --> some errors had been disabled --> checks for cable lengths (OCD call)
- SQS interloop comunication working? EEE, yes, need to investigate
- N. Jardon reminds about the default parameter procedure
- pre shutter in SA3 works commence when Zunaira, Martin and Maurizio
VAC:
XPD:
- intervention Monday in SA3, PES is operational
DET:
ITDM:
- last week new DAQ deplyoed in HED, FXE and SPB and tunnels, the three other instruments had been delayed
- scratch space in gpfs --> running out of space --> data needs to be removed
- procedure not yet agreed upon
- all involved parties should identify data that can be removed from scratch
- 100 TB are left
- internal proposals for commissioning time needed
- in the future please prepare those in advance
XRO:
- during the weekend, XRO was recommissioning of the beam transport
- some qctivities were completed on Tuesday, M3 repositioned from damaged spot
- recommissioning is completed --> however small problems are to be expected over the frst few days, please contact XRO
LAS:
UNSYS:
- cell 33 in SA2 communication crippled, ZZ planned for next monday
SPB:
- reasonably succesful first night with beam, instrument aligned with alignment laser
- tunnel EPS system --> the FXE_XTD9_popin blocked SPB to 1 pulse
- MPS signals from SPB might be masked by the machine -> needs to be checked
- 1 OCD call to EEE
- dMigration to influxDB can be done
FXE:
- re align beam to FXE pop in
- mono re alignment
- issue with FastValva --> naming convention on the PLC level had been changed, now only capital letters are allowed --> Bernard is looking into this
- tunnel project using step function with motors throws an error on the slot
- CTRL is workig on a fix already, it happens for very small steps
- J. Nardon: was also reported by SQS
- all TView devices had to be restarted as they were out of sync
MID:
- alignment went smooth, until diagnostic endstation
- data loggers are fine today to migrate to influxDB
- Steffen aims at afternoon
- pre shutter
- for CRL2 not possible to laign as the pre shutter always moved in
HED:
- beamline aligned
- beam profile excellent in fornt of hutch
- spatial jitter present, and horizontal movement
- mirror feedback macro not working
- XGM investigation together twith Theo
- IPM didodes are not read out --> comment by Peter, check the timers
-
SCS:
SQS:
- beam from around noon, beamline aligned, set points on imagers need to be re found
|
146
|
27 Jul 2020, 09:05 |
Andreas Galler | General | Information | Notes XO Integration Meeting 27.07.2020 |
General Announcement:
- XO discusses the need for sharing information.
CTRL:
- support calls
- small movements cause errors on MC2 motors, fis is going to be tested today and it will be communicated when ti is going to beployed
- swithcing to influxDB only logging, if not heard otherwise then this should happen this afternoon (Monday)
- switching to influxDB in SA1, SA2 and SA3 to follow as well
- notification service updated such, that only more serious messafe are being send out
DA:
EEE:
- cable installations in this week at HED, should start from tomorrow, 1.5 days (Jörn)
- few OCD calls,
- soft mono in SASE3, motor not working
- mirror
- FXE motor runs into emergency stop --> fixed in the latest PC framework, but FXE is running an earlier version
-
VAC:
XPD:
DET:
- Thursday, OCD was not scheduled, despite some calls
ITDM:
- bug for big detectors in DAQ had been addressed and should be deployed soon
- this bug seems to also affect some slow detectors
- only happens when there is no slow data added to the aggregator
- data reduction effort
- one outcome: record bunch pattern in every run
- instruments are asked to include the datasource XXX_timing
- SH comments: in the future the bunch pattern information will be made available in the pipeline
XRO:
- some recommissioning last week
- sometimes mirrors are not moving
LAS:
UNSYS:
SPB:
- good run for the first wek
- trouble with detector, not being able to record darks -> fixed next day
- issue with a device that checks correct datasources
- FXE imager EPS interlock issue
FXE:
- FXE imager EPS interlock issue
MID:
- successful week
- a couple of OCD calls
- CTRL, EEE, DET, everything solved
- AGIPD trainID offset by 1 wrt to the XGM
- karabo update --> changes are incompatible with existing scenes
- e.g. number of digits
- SH comments that it would be appreciated if those issue were reported to CTRL
HED:
- no issues
- MC2 motor update, is that going to be done today?
- SH: yes and if possible for HED, then 11:30 - 13:30 would be the preferred time window.
SCS:
- exit slits did not move --> EEE OCD could help
- SCS requests tthat components are tested before tunnels are closed
- Navitar didn't work
- focussing lens lost position
- when component software is updated/upgraded, SCS would liek to see a test
- NG comments: motor parameters are sometimes wrong
- If things need to be modified, test beforehand
SQS:
|
|