SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 621     Entry time: 18 Jun 2025, 09:47
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 18.06.2025 
General Announcement:
-  LIMP-25 information: Martin Doering informs: 
1. Monday 7AM the tunnels are open but smoke extraction system tests is planned from 8AM to 10AM so that tunnels will be noisy and doors difficult to open; 
2. Men's toilettes at the XHEXP1 will be closed for maintenance and the woman's will be for dual use; 
3. HXS construction activities start next week but respecting the grace period for the first two week (no infra-structure works); 
4. New screens are installed at the tunnels entrances with info of major activities taking place at each tunnels sections; 
5. Last LIMP planning meeting on Friday 20.06 with group's representatives and news will be shared during the XO Integration Meeting. 

CTRL:
- Due to issues with Broker the plan is to upgrade MID and HED topics in coming weeks. Timeline will be shared.

DA:
- All fine at DA.

EEE:
- Performing timing tests documented in XFEL e-log; XO informs the system was rolled back to the trigger with 50Hz mains yesterday by 17:00 due to tuning activities.

VAC:
- Nothing to report.

XPD:
- FD studies ongoing this week.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- A. Trapp mentions XRO completed run of temperature tests at M2 XTD10 as planned.
- No info on watchdog tests.

LAS:
- Bringing up Laser back after 50Hz tests

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- D3 tests are ongoing and seems to be well working.

MID:
- No issues to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- D3 tests ongoing this week.

SXP:
- Not present.