Adriano Violante | General | Information | Report after dispatch meeting 09.00 | FXE:
- uTCA update has been completed by EEE on Friday evening. Information will be passed to controls for the finalization.
SCS
- The interlock system for the big sliding door has to be fixed. JTD is following up the issue with TS and SRP.
- MT will talk to VAC to clarify how to go on with the train picker integration in the tunnel.
SQS
- uTCA has been updated.
- A channel in a digitizer is bisbehaving. The issue is being fixed.
- Steinmeyer stages will be commissioned today with MS.
MID:
- SDL tests ongoing
- Hexapod controllers will be moved to the rackroom. Cables have to be pulled and only after the position of the controllers can be chosen.
- Loop12 will be updated today by EEE
EEE:
- uTCA puppet migration: Instr. done. Tunnels and balconies probably will be updated at the beginning of next year.
- SASE1 and 3 EPS loop will be updated probably today.
- PLC in SPB with issues is being worked on.
- Migration to MC2 motors has been agreed with controls, XRO, XPD. in XTD 6 XPD the upgrade will be done in KW2. For the rest a plan has to be made.
XPD:
- Some issue with the font size in the new Karabo GUI. Controls will have a look.
Controls:
- Karabo updates ongoing. SASE3 today until 13:00. SA1, 2 on Wed.
- MC2 motors updates has been started also in FXE.
- SASE3: meeting with Lasermet for the integration of interlock signals in Karabo. Controls has handed over the scenes to the instruments that will optimize them.
- firmware of the power supply for the AGIPD has to be updated urgently (by Wed.). CY sent a mail to AM. If no reply the power supplies will be switched off for the update.
|
93
|
18 Dec 2019, 10:06 |
Adriano Violante | General | Information | Report after tech. Int. meeting 09.30 | MID:
- SDL tests ongoing. Important motors have been tested. Alignment of the mechanics with the alignment laser ongoing. Will be pumped over Christmas.
EEE:
- uTCA puppet migration: Instr. done. Tunnels and balconies probably will be updated at the beginning of next year.
- SASE2 EPS loop will be updated probably today.
- SPB/SFX is getting a new CPU.
- Migration to MC2 motors has been agreed with controls, XRO, XPD. in XTD 6 XPD the upgrade will be done in KW2. For the rest a plan has to be made.
ITDM
- Meeting this week ITDM/EEE/TS to discuss how to mitigate issues caused by accidents (e.g. cooling water interruption caused by power cut).
Controls:
- CY sent a mail several weeks ago to XO and the DH. The topic is emergency procedures during Christmas. No reply. CY announces that in the period 23.12-07.01 the Controls OCDs would not be available.
AoB
- No dispatch meeting on 06.01. Next meeting will be the Technical Integration one on 08.01.
|
94
|
08 Jan 2020, 12:36 |
Adriano Violante | General | Information | Report of the Technical integration meeting | SPB:
- Coordinatd motion for MC2 motors is going to be rolled out by EEE soon.
FXE:
MID:
- SDL tests ongoing.
- All SDL cables have been installed and tested apart from 6 cables (still waiting for pins to be delivered).
- Various loops update and hexapod integration ongoing.
- CRLs - EPS loop will be update probably this week. (involves position sensors in the y direction for CRLs in SASE2 and 1. To be done in the framework of the full beam operation project)
EEE:
- SA1 VAC loop update. Issues with the eplan export. Discussion ongoing with VAC and XPD.
- SA2 MOV loop update for imagers MC2 motors. This week a meeting with all the stakeholder will be held (MID, HED, EEE, Controls) and a suitable date (during next week) for the update will be found. PMO will ask MDommach to provide some feedback on the Tunnel closing schedule. As soon as the feedback is available, it will be distrubuted through the readiness mailing list.
|
|