Group Selection Page HELP Controls Group Data Analysis Group ITDM WP76 DET Vacuum EEE WP78 FXE SPB HED SQS SXP Sample Environment Operation PSPO XO TS Migrated2Zulip
Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 625     Entry time: 02 Jul 2025, 10:03
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 02.07.2025 
General Announcement:
- M. Doering announces on the LIMP-25: 
1. Old's AIBS removal is starting already this week (today), after agreement between Inaki de Diego and instruments; 
2.This Saturday 5.07 the shaft building 3 has a training for the fire brigade so no work can be done in this shaft building; 
- M. Doering announces for next week: 
1. Tunnel racks will be opened; 
2. EEE racks in balcony rooms and Laser rooms will be OFF; 
3. Cooling water: MID cooling water will be placed OFF next week; 
3. Electricity: affecting SA1 (9-10.07) and SA2 afterwards; UPS work on 12-13.07 will affect the DACHS system (no access to Experimental Hall and emergency OFF of lab levels).
- Above info can be found at Alfresco's XO page.
- A. Galler announces machine has been warmed up.

CTRL:
- Nothing to report.

DA:
- All quiet at DA.

EEE:
- Nothing to report.

VAC:
- All fine accordingly to the plan.

XPD:
- Everything fine.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- SA2: the monochromator space for rack installation is free; also valid for SA1.
- SA1: undulator moved from cell#17 to cell#1.
- SA2 crates from cell#1 and cell#2 to downstream are not yet free for move (expected to happen in about 2-3 weeks).

SPB:
- Preparing for the ramp down.

FXE:
- All was ramped down and preparing for switching OFF next week.

MID:
- Nothing to report.

HED:
- Finishing with ramp down until Friday.

SCS:
- Bringing beamline to shut down.

SQS:
- Not present.

SXP:
- Not present.
ELOG V3.1.4-7c3fd00