General Announcement:
- A. Galler informs on the LIMP-25 for next week:
1. Water: dirty traps maintenance ongoing in all tunnels but without interruptions, only changes in water pressure;
2. Limited AC and humidification control is expected;
3. Central hot water maintenance ongoing;
4. PLC updates ongoing in some areas (SA1/3 tunnels);
5. Last instrument racks ramping up next week;
6. No electricity interruptions are planned for next week.
- M. Prollius informs that constructions in the campus / roads near the shaft buildings will be taking place in order to investigate water leakage. Please be careful when using the back entrances or
biking in the campus.
- O. Bilani reminds groups to inform her when companies are planned to carry work at XHEXP1.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing new from DET.
ITDM:
- Not present.
XRO:
- Not present.
LAS:
- All quiet at LAS.
UNSYS:
- Nothing to report.
- MEA surveillance availability is limited for the next week, but shall not affect UNSYS.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |