Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 629     Entry time: 16 Jul 2025, 09:51
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 16.07.2025 
General Announcement:

- Martin Doering informs on the LIMP-25 on cw30: 
1. On PLCs only the GATT will have an update next week; 
2. Ramp-up phase will start next week with tunnel racks, balcony rooms and Lasers; 
3. XHQ rack room doors will remain open next week - please do not enter rooms; 
4. SA2 HXS electrical work will finish this week; 
5. XHEXP1 UPS extension work is postponed and will not happen on 22-23.07. Once new date is available it will be communicated; 
6. Electrical work in XHQ: lab areas (level 0) being affected until 21.07; 
7. Electrical work on the XHQ offices of level 1 starts on 22.07 until 25.07; 
8. XHQ level 2 office areas are affected with electrical work from 29.07 to 01.08. 

- Martin Doering updates on the cw29 (current week): 
1. Today from 10AM to 11:30 craning activities are planned for HXS area; Electrical maintenance in E0/lab area are also affected on Thursday in the same way as today.

- Michael Prollius informs on the fire safety for SA2 experimental area: the smoke detection system is currently OFF due to the electrical work being done. 

CTRL:
- Nothing to report; Karabo to be ramped up next week from 22.07 to 25.07.

DA:
- Nothing to report.

EEE:
- Nothing major; temperatures of SA1 balcony rooms raised more than other areas - to be monitored to see if PLCs shall also be switched off.

VAC:
- Not present.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Balcony rooms being monitoring temperatures.
- Doors to the rooms are opened and there is a trend of slow raise of temperature ongoing and flow of air from the Hall to be improved with fans.

XRO:
- Nothing to report; activities are progressing as planned;

LAS:
- Progressing with tasks.

UNSYS:
- Nothing to be reported.

SPB:
- Nothing to report, all good.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Ongoing work depends on the return of electricity.

SCS:
- Emergency OFF tests were delayed and Tobias C. informed it will happen today. 

SQS:
- Nothing to report.

SXP:
- Not present.