Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 634     Entry time: 04 Aug 2025, 09:43
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 04.08.2025 
General Announcement:
- A. Galler informs on the LIMP-25: 1. TS task #7 takes place this week with firm upgrade of the building management system will affect infrastructure system for about a minute or so.
- Kristina Lorenzen reminds that 
1. External companies shall not use visitor cards; 
2. Please let room managers know if external companies are accessing or working these rooms; 
3. Please keep paths and storage places free.
- Patrick Gessler amends that external companies were letting doors open which should remain closed. 
A. Galler says it is a responsibility of the inviting person to let room managers and other affected groups to know an external company is having work here.

CTRL:
- Fast ADC issue was fixed at all places.

DA:
- Everything quiet.

EEE:
- Work in SPB AGIPD 4M ongoing from today;
- Also work at SCS parts to be done this week.

VAC:
- Everything fine.

XPD:
- Everything fine.

DET:
- Everything fine apart of the affected detector and X-ray power due to the power cut on 25.07.

ITDM: 
- Issues at IT with Desy was fixed on Friday (cooling pipe leaked affecting building). The affected computer center is primarily not used by XFEL. 

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Nothing to be reported.
- No news on MEA2 availability; A. Galler says the MEA2 was busy at Flash and could not start work at XFEL. To be enquired at RC meeting today.

SPB:
- Nothing apart of the cabling for AGIPD 4M.

FXE:
- Nothing to report.

MID:
- All PLCs are running.

HED:
- All PLCs are running.

SCS:
- DPVA3 tests ongoing.
- PLC loop 1 crashed by was fixed by Nerea J. / EEE. It runs normally over the weekend.

SQS:
- Nothing to report.

SXP:
- Not present.