Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 627     Entry time: 09 Jul 2025, 08:32
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 09.07.2025 
General Announcement:
- LIMP-25 update for this week: elevators were to be maintained this week but it is now shifted to 16-19.July. 
- A. Galler announces on the LIMP-25 regarding next week: 
1. Karabo updates take place from next week and thus are not available; 
2. Next week last racks (UNSYS) will be placed down; 
3. Cooling water is available next week impacting racks and air conditioning in XHEXP1 - please switch OFF electrical devices in the Hall to spare heating; 
4. Humidity controlled in the Hall will not be available next week, thus temperature will change in the experimental Hall; 
5. Electricity: SA2 area in XHEXP1 do not have available electricity next week; Also XHQ will be affected; 
6. Waste water affecting some areas in XHQ; 
7. DACHS in some doors will also be affected.

- Tobias Clever reminds that UPS in XHQ will happen this weekend from 12.July.
- Suren K. says the undulator control cabinets do not use cooling water and therefore it is preferable to keep them UP and running.
- Radu S. asks on the PKGs of the XHEXP1: Tobias C. says they are to be maintained accordingly to their scheduled dates.
- Ivan A. will discuss with TS about task#2 which brings down the UPS in the lab areas to find a solution to switch OFF a spectrometer. 
- A. Galler says on Monday 14.07 craning will be done in XHEXP1 and access to the HED is not possible in the morning.

CTRL:
- Karabo SA1 instruments are already down; SA3 follows tomorrow.

DA:
- Nothing to report.

EEE:
- uTCA system being updated and prepared.

VAC:
- Following LIMP plans with activities in tunnels.

XPD:
- Ongoing with activities. All fine.

DET:
- Nothing to report.

ITDM: 
- Activities are ongoing as planned. Servers in rack rooms are shut down; Next will be balcony rooms.

XRO:
- Not present.

LAS:
- Going well so far.

UNSYS:
- Everything goes as planned; spare undulators are out of XTD8.

SPB:
- Finished ramp down yesterday.

FXE:
- Nothing to report; everything downstairs are OFF and construction works start next week.
- FXE rack room has difficult access due to the construction.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Everything accordingly to the plan.

SXP:
- Not present.