Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 627
Entry time: 09 Jul 2025, 08:32
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 09.07.2025 |
|
|
General Announcement:
- LIMP-25 update for this week: elevators were to be maintained this week but it is now shifted to 16-19.July.
- A. Galler announces on the LIMP-25 regarding next week:
1. Karabo updates take place from next week and thus are not available;
2. Next week last racks (UNSYS) will be placed down;
3. Cooling water is available next week impacting racks and air conditioning in XHEXP1 - please switch OFF electrical devices in the Hall to spare heating;
4. Humidity controlled in the Hall will not be available next week, thus temperature will change in the experimental Hall;
5. Electricity: SA2 area in XHEXP1 do not have available electricity next week; Also XHQ will be affected;
6. Waste water affecting some areas in XHQ;
7. DACHS in some doors will also be affected.
- Tobias Clever reminds that UPS in XHQ will happen this weekend from 12.July.
- Suren K. says the undulator control cabinets do not use cooling water and therefore it is preferable to keep them UP and running.
- Radu S. asks on the PKGs of the XHEXP1: Tobias C. says they are to be maintained accordingly to their scheduled dates.
- Ivan A. will discuss with TS about task#2 which brings down the UPS in the lab areas to find a solution to switch OFF a spectrometer.
- A. Galler says on Monday 14.07 craning will be done in XHEXP1 and access to the HED is not possible in the morning.
CTRL:
- Karabo SA1 instruments are already down; SA3 follows tomorrow.
DA:
- Nothing to report.
EEE:
- uTCA system being updated and prepared.
VAC:
- Following LIMP plans with activities in tunnels.
XPD:
- Ongoing with activities. All fine.
DET:
- Nothing to report.
ITDM:
- Activities are ongoing as planned. Servers in rack rooms are shut down; Next will be balcony rooms.
XRO:
- Not present.
LAS:
- Going well so far.
UNSYS:
- Everything goes as planned; spare undulators are out of XTD8.
SPB:
- Finished ramp down yesterday.
FXE:
- Nothing to report; everything downstairs are OFF and construction works start next week.
- FXE rack room has difficult access due to the construction.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Everything accordingly to the plan.
SXP:
- Not present. |