SPB:
- Coordinatd motion for MC2 motors is going to be rolled out by EEE soon.
FXE:
MID:
- SDL tests ongoing.
- All SDL cables have been installed and tested apart from 6 cables (still waiting for pins to be delivered).
- Various loops update and hexapod integration ongoing.
- CRLs - EPS loop will be update probably this week. (involves position sensors in the y direction for CRLs in SASE2 and 1. To be done in the framework of the full beam operation project)
EEE:
- SA1 VAC loop update. Issues with the eplan export. Discussion ongoing with VAC and XPD.
- SA2 MOV loop update for imagers MC2 motors. This week a meeting with all the stakeholder will be held (MID, HED, EEE, Controls) and a suitable date (during next week) for the update will be found. PMO will ask MDommach to provide some feedback on the Tunnel closing schedule. As soon as the feedback is available, it will be distrubuted through the readiness mailing list.
|