Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 630     Entry time: 21 Jul 2025, 09:54
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 21.07.2025 
General Announcement:
- M. Doering informs on the Limp-25 / current week: 
1. Cooling water maintenance in XHPSC: replacement of valves taking place and the filling back is ongoing; expected that cooling water will be back today. 
2. Temperature in XHEXP1 showed 23.8C and 64% humidity as of Friday 18.07. When cooling water is back today please wait as humidity is too high and condensation may happen; 
dehumidifying system is still limited due to maintenance but precision air conditions will return and help with dehumidification in Hall and labs. 
3. Due to construction for HXS please avoid entering or leaving XDT7 to XHEXP1.

- Janusz Szuba asks on the cooling water redundant pumps: until the end of the current week the redundant system will not work and there is a risk that primary pumps go OFF in case of a power outage.
Unclear how long it takes to recover the system in case of this failure (depends if happens during day or night). As consequence the rack rooms may be affected due to heat. To be further discussed.

- O. Bilani reminds on the safety measures around the FXE hutch constructions and please be respecting safety rules; On Wednesday morning craning activities will take place between truck bay and Hall. 

CTRL:
- Nothing major to report.

DA:
- All fine at DA.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Racks in XTD10 were closed after Thursday - rack 3.13 especially. Back doors were opened.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- No particular problems to report.

LAS:
- Air conditioning did not start at the lab E0.504 on Friday; Martin Doering will discuss with LAS - it likely to be a misunderstanding.

UNSYS:
- Nothing to report.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing to report.

SCS:
- Nothing to report; emergency test was successful.

SQS:
- Nothing to report.

SXP:
- Not present.