Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 624     Entry time: 30 Jun 2025, 09:58
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 30.06.2025 
General Announcement:
- M. Doering announces one schedule change on the test of mobile electrical equipment during the LIMP-25: 
Company doing it finished Desy premises earlier and from this week they start at EuXFEL in offices and then on the labs. If you have equipment to be tested on the offices please place them in the office 
desks.

CTRL:
- On Friday an incident happened with an unexpected reboot of a Broker machine that made SA3 and SA3-LAS Karabo loops to restart.

DA:
- Not present.

EEE:
- Nothing to report.

VAC:
- Everything fine.

XPD:
- Everything going as planned.

DET:
- Busy with SPB AGIPD-1M exchange modules; it went OK and cable fixation is also done. A test of one module shows unstable connection and needs further work. 
Further tests will be done after infrastructure tasks are finished and back.

ITDM: 
- On Friday one Broker lost the power cable - reason for reboot.

XRO:
- Going as planned.

LAS:
- Everything going well so far.

UNSYS:
- Relocation of undulators and control system are ongoing; planned to be finished this week.

SPB:
- Nothing to add apart of AGIPD-1M.

FXE:
- Not present.

MID:
- Nothing to report.

HED:
- Preparing for the LIMP-25. Being powered OFF until Wednesday.

SCS:
- Starting with maintenance.

SQS:
- Not present.

SXP:
- Not present.