General Announcement: - Martin Doering announces on the LIMP-25 (Main infrastructure works are ending in general): 1. Water related activities will be finished this week; 2. Air conditioning will work again next week; 3. Guest House also will be opening again next week; 4. Electricity: tasks are finishing next week and minor tasks in SA1 and SA3 instruments will be discussed to be scheduled in future; 5. PLC updates are still ongoing in tunnels over next week; 6. AIBS and Air Boxes will be reinstalled next week; 7. MKK2 cooling water pump replacement in XHEXP1 takes place (there is a redundant pump system so it is a task without impact). - M. Prollius says the NDR TV crew will be at XFEL after lunch and will go to XTD1 by 13:00, maybe also at XHEXP1. CTRL: - Nothing to report. DA: - Nothing to report. EEE: - Nothing apart of the PLC updates (see above). VAC: - Not present. XPD: - Nothing to report. DET: - X-ray pulse source that suffered from the power cut: depends on experts return from holidays. ITDM: - Nothing to report. XRO: - Not present. LAS: - Nothing to report. UNSYS: - Not present. SPB: - Nothing to report. FXE: - Not present. MID: - Nothing to report. HED: - Not present. SCS: - Not present. SQS: - Nothing to report. SXP: - All good at SXP.