187
|
16 Dec 2020, 09:11 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 16.12.2020 | General Announcement:
- Today is the last
xo-integration meeting for this year. Xo |
|
188
|
06 Jan 2021, 09:05 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 06.01.2021 | General Announcement:
Due to work restrictions,
some of shutdown activities will not end |
|
193
|
25 Jan 2021, 09:28 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 25.01.2021 | General Announcement:
- Test of automatic switch
of power bridge is shifted to Feb.2: this |
|
194
|
27 Jan 2021, 09:08 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 27.01.2021 | General Announcement:
- FFP2-Masks needs to be used in
the experiment control hutches from now on |
|
195
|
01 Feb 2021, 09:06 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 01.02.2021 | General Announcement:
- The test of the emergency automatic
switch of power bridge is scheduled for Tuesday, 2nd |
|
196
|
03 Feb 2021, 09:26 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 03.02.2021 | General Announcement:
- Automatic Power Switch Testing
was done yesterday. The switches are working |
|
197
|
08 Feb 2021, 08:30 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 08.02.2021 | General Announcement:
- XTD10 tunnel was closed
last Friday; XTD9 to be closed by end of |
|
198
|
10 Feb 2021, 09:20 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 10.02.2021 | General Announcement:
- Tunnel closure: it has been
decided both XTD6 and XTD9 will be searched |
|
200
|
17 Feb 2021, 09:27 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 17.02.2021 | General Announcement:
-
CTRL: |
|
202
|
24 Feb 2021, 09:03 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 24.02.2021 | General Announcement:
- Due to a failure alarm in the
smoke extraction system in XTD6+8+9, Desy |
|
204
|
03 Mar 2021, 09:23 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 03.03.2021 | General Announcement:
- Hick-ups in the beam operation
are happening since last night. There is |
|
206
|
10 Mar 2021, 09:20 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 10.03.2021 | General Announcement:
- nothing for now
CTRL: |
|
208
|
17 Mar 2021, 09:15 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 17.03.2021 | General Announcement:
- nothing.
CTRL: |
|
224
|
12 May 2021, 09:21 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 12.05.2021 | General Announcement:
- User Operations Meeting takes
place on next Friday 09:00. |
|
234
|
16 Jun 2021, 08:37 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 16.06.2021 | General Announcement:
- Interlock test next 2 weeks starting
on monday - from next wednesday the photon |
|
245
|
26 Jul 2021, 09:20 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 26.07.2021 | General Announcement:
- Power glitch 3 times at night,
what brought down the beam for 1,5 hour each |
|
246
|
28 Jul 2021, 09:29 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 28.07.2021 | General Announcement:
- No general announcement.
CTRL: |
|
87
|
27 Nov 2019, 09:25 |
Andreas Galler | General | Information | dispatch meeting Mon Nov 25 2019 | FXE: no issues
SPB: no issues
MID: Split & Delay line arriving |
|
88
|
28 Nov 2019, 15:42 |
Andreas Galler | General | Problem | affected ITDM Systems after power cut tonight |
XHQ.E1.092
SW-HH-AL-271
was available |
|
95
|
15 Jan 2020, 09:09 |
Andreas Galler | General | Information | notes Dispatch meeting Jan 13 2020 |
SPB:
Testing coordinated movement |
|