Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 15 of 31  Not logged in ELOG logo
ID Date Author Location Severity Subjectdown
  461   18 Oct 2023, 10:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.10.2023
General Announcement:
- Next Friday 20th Oct. is the deadline for submitting the Winter maintenance task list back to XO.

CTRL:
- Nothing to report.

DA:
- Nothing major to report.

EEE:
- Nothing to report.

VAC:
- Nothing from VAC.
- As PRC, Martin D. informs on the issue with the Self-seeding monochromator: X-axis is not operational. A ZZ is needed today by UNSYS. To be seen the HXRSS program.

XPD:
- Not present.

DET:
- Nothing to be reported.
- Jungfrau calibration and DAQ: there is nothing more from DET to be done; P. Schmidt adds that operation modes have to be adapted and there is work on progress in long term.

ITDM: 
- Nothing to add.

XRO:
- Nothing to report.

LAS:
- Technician from AMPHOS arrived yesterday and work in ongoing with SA3 PP-laser; no final conclusion yet.

UNSYS:
- All day working with the SA2 monochromator yesterday (X-axis and roll axis). It looks the X-axis is stuck or broken and in a ZZ an attempt to recover with a manipulator will be done. 
Chances are not high for a fix and if the worst-case scenario, the HXRSS for the remaining of the year may be cancelled.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Busy at beamline and worried with the HXRSS program.

HED:
- All fine at HED.

SCS:
- No outcome form PP-laser; getting a temporary laser from SXP (1030nm) and working to make it for the beamtime (no THz pump probe experiment will be possible).

SQS:
- Issue with digitizers (Smaract and PES); Being followed by EEE as was informed by DOC. For the PES it was discussed with XPD and needs further follow-up with SQS and XPD. 
In general, please contact DOC in case of operational issue or write EEE ticket if not an operational issue.
- High voltage power supply not responding at Karabo; being investigated by CTRL and will be coordinated with SQS for a fix.

SXP:
- Not present.
  269   18 Oct 2021, 10:14 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.10.2021
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- On the mention of offline calibration being slow: DA reminds to call the DOC as soon as the issue occurs. It is hard to find root causes at a later time.

EEE:
- Issue with SCS Scannery: solved during the weekend and follow up further;
- Coax cable installation in FXE to start from this Tuesday 19.10.

VAC:
- Nothing to report.

XPD:
- No issues to report; This week XPD is involved at Hard X-rays activities with 24keV in SA1 and >30keV in SA2.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Attempt to measure the beam position in SA2 this morning was missed as machine started to change parameters.

LAS:
- Not present.

UNSYS:
- Nothing to report.

SPB:
- Observed beam drift of up to 2mm on the 17.10; Theo M. confirms that horizontal direction moved up to 7mm at the XGM.

FXE:
- Nothing to add.

MID:
- All fine at MID; successful user beam time; Issues with Laser being helped during the weekend.

HED:
- Agipd-mini half back to HED; checked with DAQ; tests during this week.
- Also calibration for the single shot operation this week (Single shot with Agipd; picking only trains that have signal).
- Weekend to get 30keV beam: Zuzana K. is the main contact for communication and planning. 

SCS:
- Scanner-y issues: it does not run stable (not allowing to be used in automated motion); Beamtime successful.

SQS:
- Nothing to report.
  549   18 Sep 2024, 09:51 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.09.2024
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Nothing urgent to report;
- Managed to understand the AGIPD MID issue reported last Monday: it was an one-time event; a manual shutdown of correction devices was done and cause the errors. 
Please do not try to restart manually and use the automated procedure.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- All fine.

LAS:
- Not present due to a workshop.

UNSYS:
- All good.

SPB:
- Starting with beam operation; nothing to report.

FXE:
- All fine.

MID:
- All fine.

HED:
- All fine.

SCS:
- Nothing to report.

SQS:
- Not present.

SXP:
- Not present.
  452   18 Sep 2023, 10:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.09.2023
General Announcement:
- Differently from standard Mondays, today is a beam delivery day. The machine tuning day for cw38 takes place on Wednesday.

CTRL:
- Nothing to report.

DA:
- Quiet OCD weekend with two calls.

EEE:
- Nothing to report.

VAC:
- Friday afternoon SPB found pressure increase at SA1 solid attenuator which triggered vacuum signal. Investigation showed a bellow of one attenuator arm (arm 5; 1.2mm diamond) leaking and organized tunnel 
access;
- VAC will discuss with XRO how to monitor possible damage and possibly modify middle-layer device.  

XPD:
- Involved on Friday with XGM triggering alarm due to vacuum issue in XTD2.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to add to the solid attenuator issue.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.

SPB:
- Not present.

FXE:
- Preparing for beamtime.

MID:
- Nothing to report.

HED:
- Troubles with sample stages being addressed with EEE.

SCS:
- Not present.

SQS:
- Not present.

SXP:
- Not present.
  252   18 Aug 2021, 10:48 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.08.2021
General Announcement:
- In the aftermath of the severe power glitch, XO will be grateful if groups drop a message of what was affected in your groups. This will help us to understand effects of the latest power glitch.
- Status of machine: last night we had 2.3mJ in SA3 and 0.5mJ in SA1. Right now machine is under tuning - good chance of beam available for FDs today.

CTRL:
- Follow-up to the power glitch. CTRL had to restart the Karabo systems due to the main network to the brokers being down for minutes. Few follow-ups later that day but in general things have recovered. 
If groups experience troubles after running systems, please write ticket to CTRL.

DA:
- DA has deployed at SPB the latest Karabo 2.11.4. This concludes the cycle to all instruments.

EEE:
- Nerea J. informs Andreas K. detected that FXE imagers needs to be debugged by restarting the EPS loop. This will take out beam permission and may be organized for Monday morning. 
- Clock and control system was downgraded (confirmation from Bruno F.).

VAC:
- Nothing to report.

XPD:
- XPD had to restart manually many devices, macros and MDLs. One had to fix the broken Karabo bridges.
- No hardware and XGM gas supply were affected; they are running fine.
- SASE recovery only happened Tuesday afternoon and FD in SA2 was cancelled.
- A. Koch asks if Monday it is a good day for the IMG intervention. XO will check with MXL.

DET:
- AGIPD in SPB was the only detector ON during the power outage. It quickly recovered as it was in power voltage.
- DSSC being moved this week among SA3 instruments.

ITDM: 
- Network issue due to the power glitch (distribution layers switchers); connectivity of different parts of network affected. This in turn affected Karabo. 
- Gitlab upgrade today at 13:00.

XRO:
- M. Vannoni informs that to evaluate better tunnel devices (initially seems OK), one needs the beam back to check them in full.

LAS:
- PLCs and Karabo issues were found; in touch with EEE to make redundant power supply to PLCs. 
- Lasers went OFF and plan is to have PP-Ls available by Friday evening.

UNSYS:
- Problem with SA1/cell27 on Monday as motor drivers went in error state after the power glitch. It was recovered remotely. 
- Tables for 3keV @ 14GeV were updated on Monday.

SPB:
- Problem with Karabo and vacuum gauges (EEE is working on them).
- Problem with PP-laser shutter last week (unable to set interlock). It is now solved.

FXE:
- Detectors were OFF and therefore no issues due to the power glitch.
- Similar Karabo problems as described earlier.

MID:
- All fine at MID. Summary will of the effects of power glitch will be sent soon to XO.

HED:
- Lost the tests for the wavefront sensor as machine was down (FD). Plan to use beam tonight if it comes back. On Friday Karen A. plans to use beam for tests.
- Ulf Z. has sent a report to XO; Detectors were OFF and unaffected.

SCS:
- Not present.

SQS:
- Not present.
  326   18 May 2022, 11:02 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.05.2022
General Announcement:
- The cold compressor of the accelerator failed yesterday night at around 23:15. The current expectation is that beam shall be back on Thursday morning. 
Instruments and DRC were informed by the PRC via phone. A status entry can be found in the TTfinfo e-log, Operation-2022 e-log and XO Alfresco landing page.
- Update on the summer maintenance planning: Some groups have the review process finalized. Scheduling meetings are ongoing. 
If a group thinks it is needed to have an scheduling meeting please feel free to contact Martin Doering.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.
- SA3 PP-L parts that were not behaving properly are under investigation with LAS.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Not present.

UNSYS:
- High doses observed in Apple-X are under investigation; A plan to move undulators in the last night did not take place.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Yesterday a loop update cost time with loosing motor parameters but solved at the end.
- Broker pileup: root cause was the physical location of the board (configuration) was changed in between times. Location was changed when configuration was requested.

HED:
- Nothing to report.
SCS:
- Fast sample scanner has problems and needs to be fixed. Involved groups are informed.

SQS:
- Nothing to report.
  122   18 May 2020, 14:53 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.05.2020
General Announcement:
- Starting today 18.05 the XTD1 tunnel will be closed. It is not accessible until the summer shutdown. All other tunnels remain open.
- XO and PMO have sent a communication for updating the task list. Please indicate if tasks were already carried out. Deadline for submitting it back is Wednesday 17.05.
- SA1 instruments emergency power off on Friday 15.05: originated from PLCs on ProfiNet from Desy. 
It is still under investigation and we should make sure that sudden power off does not happen again, which may harm equipment such as detectors. 

CTRL:
- SPB informed issues on the notification service. CTRL appreciate the feedback and is working on it.
- It is planned to deploy the new Karabo 9.0 at MID this week.
- CTRL is working in few problems with Imagers (corrupted data) - data is flowing but not being displayed.

DA:
- No conflict or issues: working as planned.

EEE:
- SA1 VAC loop update is schedule for today.
- Friday power off on SA1: problem came from the Desy signals. It may require extra work at Desy - PLC cables are still disconnected.

VAC:
- No issues to be reported.

XPD:
- IMG issue with corrupted data was informed to CTRL who is investigating. SA2 IMG has to be fixed for use on next Monday 25.05.

DET:
- AGIPB detector at SPB suffers from power off but its Chiller was recovered without consequences. The detector itself has to be checked. 
- DET has placed the detectors in safe states, but there is nothing to protect the detectors against power outages.

ITDM: 
- Nothing to report. 

XRO:
- Nothing to report. 

LAS:
- SA1 PPL1 laser switched off on Friday around 14:30. The reason is possibly linked to low air flow. It remains unclear if there is any relation with the instruments 
power off.

SPB:
- Last week worked on Jungfrau and AGIPB detectors.
- Nothing else to report other than the power outage in the hutches.

FXE:
- Instrument recovered well from the power outage.
- It is planned the cabling installation for the next couple of days.

MID:
- Continuing with installation and commissioning. On Wed it is planned to check devices in XTD6.

HED:
- All work goes as expected.
- A plan for the XTD6 work will be done this week. The activity in tunnel shall take place next week.

SCS:
- Nothing to report.

SQS:
- Cabling installation is done. SQS reports that due to lack of crane operator in the group they had to wait some time until a crane operator was available. 
  153   19 Aug 2020, 12:08 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.05.2020
General Announcement:
- A. Galler reminds the audience on the daily informal BKR chat taking place at 15:00: link was sent by e-mail. 

CTRL:
- Tests on the HED bunch patter / 5Hz were done yesterday;
- Five devices related to the timing server will be re-started on Monday. This update of timing server shall be transparent.
- Other requests will be discussed separated in another rounds with respective involved groups.
- For Laser switch between SCS/SQS please call LAS OCD for troubleshooting (experts mean faster solutions). 

DA:
- DA reminds the group on its Redmine ticketing system that was implemented in February and helps on the planning and scheduling of activities. Instruments are encouraged 
to use the DA ticket system.

EEE:
- Initial test with HED 5 Hz pulse on demand went successfully yesterday.
- Missing crate in HED will be installed.
- SCS installation of cables will be done. 
- The special trigger for overlapping bunch in SQS was fixed this morning. CTRL was asked to prepare another parameter in Karabo. 
This shall be OK and tomorrow it shall be fine to use the adjusting the timing. S. Hauf points a device has to be adjusted. 
- A. Galler informs the tentative date for the SEPS update will be next Monday. 

VAC:
- ZZ done on Monday to check status of SA3 devices.

XPD:
- X-ray PES undergoing tests at Petra-III / Desy.
- A SQS pop-in could not be driven out of the limit switch this night. This was solved in the morning (back to work) and it was related to a problem with motor counts. 

DET:
- Preparation for user run at SQS: still some data to be taken with DSSC but it has been under work.

ITDM: 
- Together with CTRL and DA, it was set dedicated server for logging in to get more insight in the experiment. 
- In the main page of user proposal there is a permanent Zoom link to be used for communication with users. It stays for 2 weeks: SQS is working and other two experiments 
will be set today.
- In addition each experiment will have a dedicated zoom room.

XRO:
- SA1 M1 continues stay in place. By the other side, XRO would like to ask for a ZZ to complete the chiller level.
- Interlock tests in SA3 did not happened (changing of Interlock from GATT to pre-shutter) Z. Ansari informs that from her side it can take place on Monday 24th.

LAS:
- SA1 laser: the front-end is switching off in regular base (3x since Monday). There is not enough power for experiment. 
Meeting with manufacture take place today at 10 to build strategy to investigate and decide next steps. LAS will inform next steps. 
PP-laser is expected to be working for this and coming weeks. 
- SA3 Amphos: it can be operated. A final fix will be done in the in next blue weeks or during winter shutdown. 
- SA2 laser is fine.

UNSYS:
- Nothing to report.

SPB:
- Working on CRL alignment and also testing of camera. 
- Some alignment activities were interrupted due to the Laser issue. At 20% lower energy, it is not enough. Impact on commissioning if laser is not back may affect user 
experiments later. 

FXE:
- Nothing to report.

MID:
- Commissioning of the split delay line: lower branch is successfully done.

HED:
- Setting up for experiment; few issues with diodes.

SCS:
- Nothing to report.
- XO reminds the protocol to increase bunch numbers out of what is agreed on the delivery tables: 1. try to discuss with other experiment first; 2. call the PRC.

SQS:
- The zoom account was tested last night.
- Meeting with DET today. 
- All are going fine.
  499   18 Mar 2024, 09:58 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.03.2024
General Announcement:
- Machine is currently down due to the file system issues / controls. People are working with priority to recovery systems.

CTRL:
- Nothing to report;
- DAQ Uodate: Steffen Hauf informs the new DAQ version at SPB/SFX running last week had issue with data aggregator on Saturday. Debugger output is being performed in the nights at SPB; 
Deployment at MID will be discussed; Data reduction inconsistencies need to be further checked with SPB/SFX.

DA:
- Nothing to report; quiet week with DA/DOC.

EEE:
- Nothing to be reported.

VAC:
- Not present.

XPD:
- Everything working good with XPD.

DET:
- AGIPD at SPB/SFX: 1 module was lost last week and excluded of the operation (top module); correlated to when quadrants were moved; 
Changing of config and inspection will be done from tomorrow; there is a chance we run with only 15 modules until end of the run. There is no spare module to be replaced.
- Chiller at SPB/SFX was exchanged and running now.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Not present.

UNSYS:
- Everything is fine.

SPB:
- Already reported: Back to old DAQ; AGIPD module missing (top corner) - would be important for PCS beamtime.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Nothing to report; user experiment ongoing fine; happy users.

SCS:
- Two dewars of liquid nitrogen are requested for liquid jet experiments - Hall Crew will prepare dewars.

SQS:
- Nothing to report.

SXP:
- Not present.
  387   18 Jan 2023, 11:37 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.01.2023
General Announcement:
- The 5Hz tests were successfully completed. Contrary to the original schedule all tests (pure and hybrid) were finished yesterday already. 
From now on the rep rate is set back to 10Hz. If you were affected during the tests please contact XO. 
- Machine starts up with 11.5GeV from January 30th.

CTRL:
- The requirement to add the associated karabo device name to the Master Equipment List before requesting the network registration of the device is not needed anymore. 
Please suggest the karabo name directly in the network registration form. 
In case of doubts please contact Wajid E.; J. Szuba adds the network registration form in XIM is changed (Karabo name is now optional). It shall be used when an ALIAS is needed.
- Karabo framework is being worked today. 

DA:
- Preparing for bring up days next week.

EEE:
- Nothing to report.

VAC:
- Closing XTD6 and XTD9 today after lunch.

XPD:
- Finishing tunnel activities.

DET:
- Nothing to report.

ITDM: 
- UBuntu22 DOOCS JDDD is being updated today.

XRO:
- Nothing to report.

LAS:
- All good and no interruptions from the 5Hz tests.

UNSYS:
- Currently performing middle plane scans in SA1 and SA2.

SPB:
- Nothing to report.

FXE:
- Aligned XTD9 cameras and Mono. One power supply did not work and Beckhoff devices of all FXE tunnel components did not work; Wajid E. informs this was because of wrong Alias.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Agilent turbo pump shows a Karabo problem. EEE will be contacted.
  191   18 Jan 2021, 09:44 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.01.2021
General Announcement:
- Clarification on the definition of a critical work will be made this afternoon during a discussion with group leaders and will be communicated to the staff. 
It includes also tasks carried out by two different groups.
- On Thursday there is going to be a switch of MPS components in the balcony room. 
This affects the timing signal distributed to XFEL, e.g. Lasers will not be able to follow timing. 
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute).
General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets. 
This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.

CTRL:
- CTRL enquires ITDM on the issue with DOC (disk space full error). ITDM will take a look into it. 

DA:
- Getting prepared for involvements such as the data operation center.

EEE:
- Update of SA1 loop motion to take place by Wednesday. Affected staff is already informed.
- Firma Wille work on cabling is ongoing.

VAC:
- Continuing with works in the tunnels.

XPD:
- Tunnels works in XTD6 and XTD9 are ongoing. No incidents to report.

DET:
- Working on data analysis calibrations and installing the DOC.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Regarding the Timing signal interruption mentioned in general announcements: it is not a problem as usually LAS keep the laser systems in the local timing during 
shutdown periods.
- Upgrading hardware that should be updated accordingly to the plans for the shutdown.

UNSYS:
- Works in tunnel are proceeding.
- Issues with SA2 cell 26 and cell27 were found and experts are going to the tunnel to solve it.

SPB:
- Working on making experimental plans for the Covid-19 beamtime.

FXE:
- Detectors: software upgrade taking place from today.

MID:
- All fine.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  279   17 Nov 2021, 11:20 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.11.2021
General Announcement:
- XO will publish on Friday the full maintenance task list. Everyone is invited to also look at the Infrastructure calendar which contains main dates on this topic. 
Please contact XO in case you have questions. The task list will be published via e-mail containing also the file location in an Alfresco folder.
- A power glitch was observed today at around 07:40AM. Machine was not affected. Please check your systems.
- Jan G. asks on Zoom operation issues seen yesterday (link of PBS meeting was shared with non-XFEL staff). 
K. Wrona says that this particular case the link was posted at the website including the password and everyone from the world could access. ITDM will prepare an e-mail describing good working practices.

CTRL:
- No major updates.

DA:
- No major updates.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Systems were checked after this morning's power glitch and they seem fine. 
- The transmissive imager (Diamond screens) in SA1 and SA2 are still in. To remove them the instruments shall contact Andreas Koch.

DET:
- Nothing to report.

ITDM: 
- ITDM expects this week a lot of data for the user experiments that may overflow systems. ITDM is preparing contingency space for it. 

XRO:
- Nothing to report.

LAS:
- No effects were seen from the power glitch; lasers are running.

UNSYS:
- Last Monday the ZZ access in SA3 (cell#22) was successful and the Phase Shifter motor was exchanged. Currently discussions are taking place to evaluate counter-measures for the case it is related to 
radiation damage.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Nothing to report.

SCS:
- Nothing to report.

SQS:
- Nothing to report.
  366   17 Oct 2022, 09:31 Andreas GallerGeneralInformationNotes XO Integration Meeting 17.10.2022

General Announcement:

  •  

CTRL:

  • nothing major

DA:

  • nothing special

EEE:

  • OCD call on Friday
    • ion pump controller broken in XTD1

VAC:

  • see EEE --> additionally over the weekend the pump was taken out of the interlock

XPD:

  • nothing

DET:

  • JungFrau damagat at SPB/SFX in cw 40
    • two powder rings permantnly burned into detector

ITDM:

  • SA2 online system (gpfs) one enclosure is bahving strangely, --> fixed no replacement needed

XRO:

  • nothing to report

LAS:

  • crash of PPLaser in SA1 over the weekend
    • TRGDly was upgraded recently/ crashed for SPB --> TRGDly device being rolled back and PPLAS1 should be back up today.

UNSYS: 

  • ccell 25 SA1 fixed --> now only 6 motors are left.
    • Lead shields ETA beginning of February --> will have to be done through ZZ
    • broken motors and encoders are sent back to Beckhoff
      • repair time approx. 2 - 3 months

SPB/SFX:

  • Jet control stopped
  • PPLAS
    • on Friday there was no LAS output --> fixed
      • no LAS OCD in blue weeks, and on Friday no LAS group member on site --> earliest service on Saturday through good will.
    • shift change not successful due to miscommunication
      • SPB let the laser run over night for measurements --> FXE did shift change over night eventually destroying the SPB measurement
    • see LAS TRGDLY device
  • SPB requests to not upgrade software thorugh run for PPLasers.
    • recently there were some upgrades on a Monday which then later fail for operation
  • SPB notest that there is only limited OCD by LAS group and then LAS cannot cover critical components

FXE:

  • set up built for User Experiment
    • HallCrew supported in build up
    • LAS use --> see SPB/SFX

MID:

  • all fine at MID

HED:

  • user experiment being set up

SCS:

  • not present

SQS:

  • nothing to report

DRC

  •  

PRC

  •  

  350   17 Aug 2022, 11:19 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.08.2022
General Announcement:
-  Machine is currently set at 12 GeV to best accommodate the requests for the next 3 weeks.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- SA1-PP laser update is done and no problems are seen now.

VAC:
- Nothing to report.

XPD:
- Jan G. informs as PRC the machine had difficulties to tune SA1 and SA2 yesterday. However overnight intensities improved by a factor 2 and are now higher or equal than 1 mJ (6keV at SA1 and 9keV in SA2).

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- Nothing to report.

SPB:
- Started using beam to pre-align mirrors last night.
- Intensity is lower than expected to start with. To be seen if user program will be affected.

FXE:
- FXE performed the work as planned last weekend. When changing undulator gap on Sunday beam jitter occurred.

MID:
- Still need 352 pulses for this week; Pre-tuning at 12keV was done during the night with 500uJ intensity.
- A stage has to be implemented for the user runs together with G. Giovanetti.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Maurizio V. asks on the last week’s photon energies (lower values) and would like to discuss with SQS the performance of the beamline transport concerning the C absorption (mirrors). SQS will look 
together with XRO.
  152   14 Aug 2020, 10:40 Andreas GallerGeneralInformationNotes XO Integration Meeting 17.08.2020
General Announcement:
- An informal Run coordinators' BKR chat to exchange ideas happens every day at 15:00. 
It is a forum in case technical and scientific people wish to make formal requests. XO will send an e-mail with Zoom link.
- XO would like to ask instruments to pay attention to the parameters of the Delivery and Operators table, especially regarding the bunch limits for the North branch.
Ideally we shall discuss one week before beam delivery.
- H. Sinn notices that if SPB move some motors, this is temporarily cutting SA3 beam due to MPS. SQS has not observed this effect. Harald will further investigate. 
Adrian M. says SCS impacts SPB in different ways.
- A. Galler mentions that SRP/task force will distribute updates related to the currently raising Covid issues.

CTRL:
- One group of motors at the same SCS/PLC was not accepting changes. A re-start with servers in small loops must help.
- Timing servers (switching off archive): CTRL wants to perform today or tomorrow morning the installation of the new version. Nobody seems against it.

DA:
- Nothing to report.

EEE:
- EEE understand the team request regarding the 5 Hz trigger will be done tomorrow.
- EEE waits for confirmation of SEPS update, possibly happening today or tomorrow. XO mentions Z. Ansari will be able to confirm today after lunch time.

VAC:
- Nothing to report.

XPD:
- Not present.

DET:
- XO inquires on the DSSC activities in SCS: DET says it may be delayed a bit due to other activities; DET got a ticket regarding operation; DA believes the DSSC was 
running and used.

ITDM: 
- Comment on DSSC: it was used but we shall not forget that on the first day there was not a preparation and we could expect hiccups.
- A faulty memory module must be replaced and the exflgateway will be shut down shortly for this activity at around 12:00. An e-mail will be sent but nobody seems against 
to it. 

XRO:
- Nothing to report.

LAS:
- SA3 AMPHOS photodiodes still has problems. System is partially working and can be operated. LAS knows beam size and pointing do not change but not if loses power. 
AMPHOS is contacted. 
The consequence is that switching ON and OFF takes more time because it is done manually. Further measurements will be done and SA 3 instruments will be updated 
accordingly.
- LAS informs its OCD team is not responsible for synchronization issues. 
- SA1 and SA2 lasers are fine.

UNSYS:
- Small issues with SA3 PLC crashes: SA3 is operated without first cells. A re-start of the servers is needed, probably today or tomorrow. UNSYS will inform SCS and SQS 
when this is fixed. 

SPB:
- Nothing to report.

FXE:
- FXE says that SQS will need to perform some tests: this will be discussed in separate round.

MID:
- All fine.

HED:
- Data recording on Saturday night was not saved. Shift crew realized at the end of the shift that it was not saved - main data for the shift. 
- ITDM investigated the issue after ticket arrived yesterday. It confirms data was not recorded and can't see why this happens as ticket arrived late. Even the folder of 
the data was not recorded. 
For the future: there is an assumption to look at the data every few minutes. ITDM will share procedures. Further discussions on flexibility for different systems/setups 
have to be done.
- HED says the 5Hz test must be tomorrow by the morning. XO states that currently this is only a test then we will see what happens. HED has this understanding.
- HED has recorded several hundreds of microns in horizontal jitter. XRO says that it is important to work together for investigating the jitter. 
HED will send the data to XRO and/or the coordinator of stability task force.

SCS:
- Not present.

SQS:
- Preparing next week user operation; still some problems with Zoom connection: SQS and ITDM will discuss the issue.
  531   17 Jul 2024, 09:50 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.07.2024
General Announcement:
- Martin Doering informs today an e-mail will be sent to groups asking for tasks that are cancelled or postponed. The feedback will be required until mid of next week.
- A. Galler informs on a report for non-correct bunch arrival monitors at the instruments. It is requested to instruments to get information on this topic and bring back to XO.
- User Operation Meeting starts next Friday 19.07.

CTRL:
- Nothing to report.

DA:
- Not present.

EEE:
- Nothing to report.

VAC:
- Not present.

XPD:
- Gotthard-II in XTD6 Hirex: today the power supply will be checked and by end of the day info to XO/PRC will be done.

DET:
- SPB/SFX an issue with Jungfrau-4M high voltage power supply system happen and is broken needing a fix.
- Hirex/Gotthard-II the tests with beam is prioritized on Monday/Tuesday next week.

ITDM: 
- Nothing to report.

XRO:
- On the weekend it starts the technical ramp-up of SA3 and Monday/Tuesday the SA2 and SA1;
- On Monday the SEPS interlock tests are happening and hutches will be closed.

LAS:
- Nothing to report.
- Bunch pattern server issue last week: fix was provided. No more info on the effects of it on LAS preparations.

UNSYS:
- Issue with SA3/cell18 undulator did not move and hit the limit. Under investigation.

SPB:
- Nothing to add to the Jungfrau issue.

FXE:
- Nothing to report.

MID:
- Issue with vacuum system at MID - failed yesterday twice.

HED:
- Nothing to report.

SCS:
- Yesterday problem with mechanics in tunnel; will need PLC team; Leandro Z. informs is under investigation.

SQS:
- Nothing to report.

SXP:
- Not present.
  435   17 Jul 2023, 09:53 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.07.2023
General Announcement:
- SEPS interlock tests are taking place today. An e-mail was sent to xo-info last Friday containing information about the order of the tests.

CTRL:
- Start with bring up days (SCS and SXP today) the whole week.
- Workaround solution for PLC/Karabo was deployed but needs to be redone tomorrow at 8AM tomorrow. An e-mail will be sent to xo-info.

DA:
- Nothing to report.

EEE:
- Bring up days and support of SEPS. 

VAC:
- Nothing to report.
- As PRC, Martin D. says on Saturday morning issues with AIBS blocked beam operation. Solved by DRC and EEE/PLC OCD.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM: 
- Data analysis of experiments (past ones): to be migrated on next week over three days. E-mail to be sent to xo-info.

XRO:
- Involved in the SEPS interlock today.
- ZZ for HED Mono was successful by power cycling device Not yet clear if camera is broken or a Karabo/PLC issue. 

LAS:
- Nothing to report.

UNSYS:
- All fine.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- PP laser work this week and then setting up beamtime for cw31.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.
  522   17 Jun 2024, 09:38 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.06.2024
General Announcement:
- Summer maintenance is about to start on Wednesday; tomorrow the XRO and XPD ramp down activities are planned. 
- The XO Integration meeting continues to happen during the summer maintenance period.

CTRL:
- Nothing to report; preparing for the summer maintenance.

DA:
- Nothing to report and quiet on the OCD side.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Nothing major to report.

ITDM: 
- Nothing to report.
- Maxwell maintenance: Likely to be done Monday/Tuesday of last week of June is the deployment. E-Mail will be sent.

XRO:
- Nothing to report.

LAS:
- Nothing to report.
- SA1 issue of last weeks with drifting: sync system maintenance was not announced and found to be the reason for it. Right now it is fixed. Also master time was reset by EEE.

UNSYS:
- Everything fine apart of the SA1/cell22 PS motor to be replaced when tunnels are open.

SPB:
- Not present due to the ongoing retreat.

FXE:
- Nothing to report.

MID:
- All fine at MID.

HED:
- Not present.

SCS:
- Start with maintenance tasks.

SQS:
- Nothing to report.

SXP:
- Not present.
  133   18 Jun 2020, 13:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.06.2020
General Announcement:
- Today and tomorrow it takes place the tunnel ventilation maintenance between 6:30 and 8:00AM;
- An e-mail was sent to readiness list with tunnel access restrictions for next Friday morning at the Osdorf Born site in and XTD4 work between 10-11AM.
- Today there the maintenance of the SA3 hutch crane is scheduled.

CTRL:
- CTRL will follow up the uTCA updates.
- Mc2 migration in SA2 is almost done - only XPD needs to test some componenents.
- CTRL is working in some layout problems in scenes of the latest GUI update (new Karabo). Groups are encouraged to write tickets to CTRL if they require changes. 

DA:
- Nothing to report.

EEE:
- Shutdown activities are ongoing with, e.g, VAC loop updates and PLC updates;
- The firmware updates affecting the PP-laser timing will take place on next Friday (19.06) in all SASEs. 
- EEE is following the delay on the MID cabling related to personal interlock. 

VAC:
- Shutdown activities in XTD6 and XTD10 are ongoing. 

XPD:
- Currently finishing own summer shutdown tasks in tunnels.
- First DAQ test together with ITDM: had to wait the timing server re-start. To be continued today also after full mc2 migration.

DET:
- Calibrations of detectors at instruments are ongoing.

ITDM: 
- Nothing to report.

XRO:
- Not present.

LAS:
- So far all in good state.

UNSYS:
- Nothing to report.

SPB:
- DAQ update was not an entire success - but it has been taken care. DAQ is needed for the calibration test of detectors.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing special.

SCS:
- Nothing to report.

SQS:
- PC updates are ongoing.
- SQS raises the question on hutch access during the disabled emergency off planned for next Monday. It is possible that SQS EQP will be in sick leave on that day. 
XO will contact Torsten Schoen to get more details on the time schedule and possible access for that day.
  419   17 May 2023, 09:40 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 17.05.2023
General Announcement:
- Change in 2024 schedule: for next year the setup days is shifted from Mondays to Tuesdays. Please keep it in mind when setting shift plans for next year. 
In case of questions please get in touch with XO.
- Currently we are in facility development week and so far mostly activities linked to the accelerator were done.
- The UOM of next Friday 19.05 does not take place.

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Everything running normally.
- Yesterday intervention at XTD6 to move collimator at MID branch: system was moved accordingly to the plan.

XPD:
- Commissioning activities ongoing.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Bringing up the AMPHOS laser and it shall be OK by the end of the week. In case of questions please address Max L.

UNSYS:
- All good.

SPB:
- Nothing to report.

FXE:
- Two vacuum leaks were found at the experiment and fixed together with VAC members.

MID:
- Preparing for experiment next week. MID is in contact with EEE to address some issues.

HED:
- Not present.

SCS:
- Preparing new timing setup.

SQS:
- Nothing to report.

SXP:
- Not present.