Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 523     Entry time: 19 Jun 2024, 09:48
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 19.06.2024 
General Announcement:
-	 

CTRL:
- Perform tests on watchdogs with XPD after this meeting.

DA:
- Nothing to report.

EEE:
- Today start with cable installations at SQS - be careful with cables when walking.
- Many tasks are ongoing.

VAC:
- Nothing to report.

XPD:
- Ramp down day yesterday by XRO and XPD; issues were identified and solved. Time was useful and successful.
- Tests with Imagers without X-ray beam are being done today.

DET:
- Start with maintenance tasks.

ITDM: 
- First day with activities on servers and clusters at balcony room.
- Maxwell update on 24.06 will be advertised by e-mail today.

XRO:
- Not present.

LAS:
- Start with shutting down lasers today.
- Safety interlock work in SA3 laser areas takes up to end of next week that requires Electrical expert present (see e-mail from Torsten S.). 
Emergency OFF button is only valid for the laser rooms/hutches in SA3.

UNSYS:
- Replace SA1 cell22 PS motor from today.

SPB:
- Not present.

FXE:
- Nothing to report.

MID:
- All fine at MID; going accordingly to the schedule.

HED:
- Nothing to report.

SCS:
- Moving experimental chamber today through the Hall.

SQS:
- Not present.

SXP:
- Not present.