SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 523
Entry time: 19 Jun 2024, 09:48
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 19.06.2024 |
|
|
General Announcement:
-
CTRL:
- Perform tests on watchdogs with XPD after this meeting.
DA:
- Nothing to report.
EEE:
- Today start with cable installations at SQS - be careful with cables when walking.
- Many tasks are ongoing.
VAC:
- Nothing to report.
XPD:
- Ramp down day yesterday by XRO and XPD; issues were identified and solved. Time was useful and successful.
- Tests with Imagers without X-ray beam are being done today.
DET:
- Start with maintenance tasks.
ITDM:
- First day with activities on servers and clusters at balcony room.
- Maxwell update on 24.06 will be advertised by e-mail today.
XRO:
- Not present.
LAS:
- Start with shutting down lasers today.
- Safety interlock work in SA3 laser areas takes up to end of next week that requires Electrical expert present (see e-mail from Torsten S.).
Emergency OFF button is only valid for the laser rooms/hutches in SA3.
UNSYS:
- Replace SA1 cell22 PS motor from today.
SPB:
- Not present.
FXE:
- Nothing to report.
MID:
- All fine at MID; going accordingly to the schedule.
HED:
- Nothing to report.
SCS:
- Moving experimental chamber today through the Hall.
SQS:
- Not present.
SXP:
- Not present. |