General Announcement:
- A. Galler asks the instruments to also take a look at the operators table as they have a shift-by-shift information for X-ray delivery, not only into the delivery tables.
CTRL:
- Influx logging update: CTRL might have found the couple of devices producing the problem. Solution has been found by restarting and synchronizing the timing clock.
DA:
- Nothing to report.
EEE:
- Nothing to report.
- MID cabling is done.
VAC:
- Nothing to report.
ME:
- Not present.
XPD:
- Nothing to report.
DET:
- Assessment of the humidity issue; minor problem with the control humidity (power supply) interlock.
- A. Galler asks when PP will be available to FXE. Answer is that there is not yet a fix date.
ITDM:
- Nothing to report.
XRO:
- Harald Sinn says the three SASEs were aligned, excluding the Monochromators. Beam is available at the end of the tunnels.
- Issue 1: at HED the M3 mirror was with Platinun strip inserted for sometime and may be damaged (it has been changed).
- Issue 2 with backlash: running in a single mode and must be two backlash – ticket issued to CTRL and may affect the MC motors. Nerea J. is aware and get in touch with Harald Sinn (info from Jorn
R.).
LAS:
- Trouble with humidity changes and can't guarantee beam pointing. Next few days one must be able to get back the proper operation. Changes from Desy originated the change and TS was not informed.
UNSYS:
- Suren K. informs that the PKG in SA3 does not work. A ZZ is needed by TS (Christian Holz). A ticket has been written for ZZ. TS has only one person allowed to go to tunnel but one UNSYS technician can
accompany TS.
SPB:
- Nothing to report.
FXE:
- Not present.
MID:
- All fine.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |