Group Selection Page HELP Controls Group ITDM Vacuum WP78 SPB SQS XO ToBeMigrated2XWiki ToBeMigrated2GitlabPages ToBeMigratedByGroup Migrated2Zulip Archived2PDF not2MigrateOrArchive
SCS SXP Migrated2Zulip Photon Commissioning Team XRO DOC HED Migrated2Zulip WP74 MID PSPO_XO XO_Operation SQS Migrated2Zulip FXE Migrated2Zulip DET Sample Environment SPB Migrated2Zulip
SASE1 Status and SASE3 Readiness Technical integration and coordination
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 491     Entry time: 19 Feb 2024, 09:55
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 19.02.2024 
General Announcement:
- As PRC Maurizio V. mentions there is nothing particularly important to report.


CTRL:
- Nothing to report.
- Steffen H. informs on DAQ: SPB run the new version and not too many issues were left - just trains were not reduced entirely and scheme updates were not available. Overall it run stable last nights.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- Nothing to report.

DET:
- Issue with Jungfrau/FXE: gain parameters were not saved in files sometimes; Fixed by refreshing the DAQ. DET is working on it. 
Fabio D.'A. confirms the strategy and there is no impediment to the instruments anymore.

ITDM: 
- Reminder for commissioning proposals from last year: there are one from SPB/SFX and one from SCS that still have to be closed. From Thursday data will be lost if not moved/copied.

XRO:
- Nothing to report.

LAS:
- Not present.

UNSYS:
- Waiting for ZZ for repairing the phase shifter in cell#12 SA3.

SPB:
- Nothing to report.

FXE:
- Jungfrau problem: FXE called DOC every time (See DA above). Steffen H. proposes to test new DAQ this week as it has no users and shall help to fix the DAQ point reported.
- Beam energy loss during the weekend.
- Pointing issues were reported on Friday.

MID:
- Issue with AGIPD when moving.
- Users are happy and taking data. 

HED:
- Preparing for beam this week with two programs.

SCS:
- Nothing to report.

SQS:
- Not present.

SXP:
- Nothing to report.
ELOG V3.1.4-7c3fd00