Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 566     Entry time: 18 Nov 2024, 09:41
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 18.11.2024 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- HAMP XGM at hard X-rays: emergency was triggered; after rebooting it worked normally.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Nothing to report.

LAS:
- Nothing to report.
- Low PP-laser pulse energy for FXE: not yet solved; needs investigation with AMPHOS - will talk to both SA1 instruments for use or time that intervention can be done.

UNSYS:
- Problem SA2 cell5: power supply distribution needed to be replaced last Thursday.

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Not present.

SCS:
- Nothing to report.

SQS:
- Not present.
- Eric Boyd mention that the AIBS box at SQS will be replaced to a spare air box on Tuesday morning.

SXP:
- Nothing to report.