499
|
18 Mar 2024, 09:58 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 18.03.2024 |
General Announcement:
- Machine is currently down due to the file system issues / controls. People are working with priority to recovery systems.
CTRL:
- Nothing to report;
- DAQ Uodate: Steffen Hauf informs the new DAQ version at SPB/SFX running last week had issue with data aggregator on Saturday. Debugger output is being performed in the nights at SPB;
Deployment at MID will be discussed; Data reduction inconsistencies need to be further checked with SPB/SFX.
DA:
- Nothing to report; quiet week with DA/DOC.
EEE:
- Nothing to be reported.
VAC:
- Not present.
XPD:
- Everything working good with XPD.
DET:
- AGIPD at SPB/SFX: 1 module was lost last week and excluded of the operation (top module); correlated to when quadrants were moved;
Changing of config and inspection will be done from tomorrow; there is a chance we run with only 15 modules until end of the run. There is no spare module to be replaced.
- Chiller at SPB/SFX was exchanged and running now.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Not present.
UNSYS:
- Everything is fine.
SPB:
- Already reported: Back to old DAQ; AGIPD module missing (top corner) - would be important for PCS beamtime.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Nothing to report; user experiment ongoing fine; happy users.
SCS:
- Two dewars of liquid nitrogen are requested for liquid jet experiments - Hall Crew will prepare dewars.
SQS:
- Nothing to report.
SXP:
- Not present. |
387
|
18 Jan 2023, 11:37 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 18.01.2023 |
General Announcement:
- The 5Hz tests were successfully completed. Contrary to the original schedule all tests (pure and hybrid) were finished yesterday already.
From now on the rep rate is set back to 10Hz. If you were affected during the tests please contact XO.
- Machine starts up with 11.5GeV from January 30th.
CTRL:
- The requirement to add the associated karabo device name to the Master Equipment List before requesting the network registration of the device is not needed anymore.
Please suggest the karabo name directly in the network registration form.
In case of doubts please contact Wajid E.; J. Szuba adds the network registration form in XIM is changed (Karabo name is now optional). It shall be used when an ALIAS is needed.
- Karabo framework is being worked today.
DA:
- Preparing for bring up days next week.
EEE:
- Nothing to report.
VAC:
- Closing XTD6 and XTD9 today after lunch.
XPD:
- Finishing tunnel activities.
DET:
- Nothing to report.
ITDM:
- UBuntu22 DOOCS JDDD is being updated today.
XRO:
- Nothing to report.
LAS:
- All good and no interruptions from the 5Hz tests.
UNSYS:
- Currently performing middle plane scans in SA1 and SA2.
SPB:
- Nothing to report.
FXE:
- Aligned XTD9 cameras and Mono. One power supply did not work and Beckhoff devices of all FXE tunnel components did not work; Wajid E. informs this was because of wrong Alias.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Agilent turbo pump shows a Karabo problem. EEE will be contacted. |
191
|
18 Jan 2021, 09:44 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 18.01.2021 |
General Announcement:
- Clarification on the definition of a critical work will be made this afternoon during a discussion with group leaders and will be communicated to the staff.
It includes also tasks carried out by two different groups.
- On Thursday there is going to be a switch of MPS components in the balcony room.
This affects the timing signal distributed to XFEL, e.g. Lasers will not be able to follow timing.
- Test of automatic switch of power bridge is shifted to Feb.2: this affects all devices connected to orange or green power sockets (no power for few seconds/minute).
General e-mail will be sent. Instruments will need to care for equipment which is connected to these sockets.
This also affects the E0 level as well as office space in XHQ. Pease plug devices out or re-plug in other sockets.
CTRL:
- CTRL enquires ITDM on the issue with DOC (disk space full error). ITDM will take a look into it.
DA:
- Getting prepared for involvements such as the data operation center.
EEE:
- Update of SA1 loop motion to take place by Wednesday. Affected staff is already informed.
- Firma Wille work on cabling is ongoing.
VAC:
- Continuing with works in the tunnels.
XPD:
- Tunnels works in XTD6 and XTD9 are ongoing. No incidents to report.
DET:
- Working on data analysis calibrations and installing the DOC.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Regarding the Timing signal interruption mentioned in general announcements: it is not a problem as usually LAS keep the laser systems in the local timing during
shutdown periods.
- Upgrading hardware that should be updated accordingly to the plans for the shutdown.
UNSYS:
- Works in tunnel are proceeding.
- Issues with SA2 cell 26 and cell27 were found and experts are going to the tunnel to solve it.
SPB:
- Working on making experimental plans for the Covid-19 beamtime.
FXE:
- Detectors: software upgrade taking place from today.
MID:
- All fine.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
279
|
17 Nov 2021, 11:20 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.11.2021 |
General Announcement:
- XO will publish on Friday the full maintenance task list. Everyone is invited to also look at the Infrastructure calendar which contains main dates on this topic.
Please contact XO in case you have questions. The task list will be published via e-mail containing also the file location in an Alfresco folder.
- A power glitch was observed today at around 07:40AM. Machine was not affected. Please check your systems.
- Jan G. asks on Zoom operation issues seen yesterday (link of PBS meeting was shared with non-XFEL staff).
K. Wrona says that this particular case the link was posted at the website including the password and everyone from the world could access. ITDM will prepare an e-mail describing good working practices.
CTRL:
- No major updates.
DA:
- No major updates.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Systems were checked after this morning's power glitch and they seem fine.
- The transmissive imager (Diamond screens) in SA1 and SA2 are still in. To remove them the instruments shall contact Andreas Koch.
DET:
- Nothing to report.
ITDM:
- ITDM expects this week a lot of data for the user experiments that may overflow systems. ITDM is preparing contingency space for it.
XRO:
- Nothing to report.
LAS:
- No effects were seen from the power glitch; lasers are running.
UNSYS:
- Last Monday the ZZ access in SA3 (cell#22) was successful and the Phase Shifter motor was exchanged. Currently discussions are taking place to evaluate counter-measures for the case it is related to
radiation damage.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Nothing to report.
SCS:
- Nothing to report.
SQS:
- Nothing to report. |
366
|
17 Oct 2022, 09:31 |
Andreas Galler | General | Information | Notes XO Integration Meeting 17.10.2022 |
General Announcement:
CTRL:
DA:
EEE:
- OCD call on Friday
- ion pump controller broken in XTD1
VAC:
- see EEE --> additionally over the weekend the pump was taken out of the interlock
XPD:
DET:
- JungFrau damagat at SPB/SFX in cw 40
- two powder rings permantnly burned into detector
ITDM:
- SA2 online system (gpfs) one enclosure is bahving strangely, --> fixed no replacement needed
XRO:
LAS:
- crash of PPLaser in SA1 over the weekend
- TRGDly was upgraded recently/ crashed for SPB --> TRGDly device being rolled back and PPLAS1 should be back up today.
UNSYS:
- ccell 25 SA1 fixed --> now only 6 motors are left.
- Lead shields ETA beginning of February --> will have to be done through ZZ
- broken motors and encoders are sent back to Beckhoff
- repair time approx. 2 - 3 months
SPB/SFX:
- Jet control stopped
- PPLAS
- on Friday there was no LAS output --> fixed
- no LAS OCD in blue weeks, and on Friday no LAS group member on site --> earliest service on Saturday through good will.
- shift change not successful due to miscommunication
- SPB let the laser run over night for measurements --> FXE did shift change over night eventually destroying the SPB measurement
- see LAS TRGDLY device
- SPB requests to not upgrade software thorugh run for PPLasers.
- recently there were some upgrades on a Monday which then later fail for operation
- SPB notest that there is only limited OCD by LAS group and then LAS cannot cover critical components
FXE:
- set up built for User Experiment
- HallCrew supported in build up
- LAS use --> see SPB/SFX
MID:
HED:
- user experiment being set up
SCS:
SQS:
DRC
PRC
|
649
|
17 Sep 2025, 09:40 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.09.2025 |
General Announcement:
- F. Wolff-Fabris comments on the LIMP-25: for cw38 schedule sees:
1. the PLC updates as main activity;
2. Karabo upgrade in October with tests being carried out this week at MID;
3. One pump in the KW20 circuit is being serviced from today (17.09) and thus no redundancy exists for one week. The KW20 water is supplied normally in this period.
- Two short power glitches were detected at DESY yesterday (17.09) morning. We are not aware of any disturbances at the campus but please let XO know if you were affected.
CTRL:
- Started MID migration last Monday and Tuesday. It was successful and no major issues happened, only few devices still missing; minor issues with Beckhoff. All identified and a fix to be done
today/tomorrow.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Not present.
XPD:
- Nothing to report.
- PLC was updated in SA1 and VC loop also. Few hours of pressure increase but still manageable and went fine.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Not present.
UNSYS:
- Everything is fine; Installation is ongoing.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Not present.
SQS:
- Not present.
SXP:
- Not present. |
350
|
17 Aug 2022, 11:19 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.08.2022 |
General Announcement:
- Machine is currently set at 12 GeV to best accommodate the requests for the next 3 weeks.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- SA1-PP laser update is done and no problems are seen now.
VAC:
- Nothing to report.
XPD:
- Jan G. informs as PRC the machine had difficulties to tune SA1 and SA2 yesterday. However overnight intensities improved by a factor 2 and are now higher or equal than 1 mJ (6keV at SA1 and 9keV in SA2).
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
UNSYS:
- Nothing to report.
SPB:
- Started using beam to pre-align mirrors last night.
- Intensity is lower than expected to start with. To be seen if user program will be affected.
FXE:
- FXE performed the work as planned last weekend. When changing undulator gap on Sunday beam jitter occurred.
MID:
- Still need 352 pulses for this week; Pre-tuning at 12keV was done during the night with 500uJ intensity.
- A stage has to be implemented for the user runs together with G. Giovanetti.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Maurizio V. asks on the last week’s photon energies (lower values) and would like to discuss with SQS the performance of the beamline transport concerning the C absorption (mirrors). SQS will look
together with XRO. |
152
|
14 Aug 2020, 10:40 |
Andreas Galler | General | Information | Notes XO Integration Meeting 17.08.2020 |
General Announcement:
- An informal Run coordinators' BKR chat to exchange ideas happens every day at 15:00.
It is a forum in case technical and scientific people wish to make formal requests. XO will send an e-mail with Zoom link.
- XO would like to ask instruments to pay attention to the parameters of the Delivery and Operators table, especially regarding the bunch limits for the North branch.
Ideally we shall discuss one week before beam delivery.
- H. Sinn notices that if SPB move some motors, this is temporarily cutting SA3 beam due to MPS. SQS has not observed this effect. Harald will further investigate.
Adrian M. says SCS impacts SPB in different ways.
- A. Galler mentions that SRP/task force will distribute updates related to the currently raising Covid issues.
CTRL:
- One group of motors at the same SCS/PLC was not accepting changes. A re-start with servers in small loops must help.
- Timing servers (switching off archive): CTRL wants to perform today or tomorrow morning the installation of the new version. Nobody seems against it.
DA:
- Nothing to report.
EEE:
- EEE understand the team request regarding the 5 Hz trigger will be done tomorrow.
- EEE waits for confirmation of SEPS update, possibly happening today or tomorrow. XO mentions Z. Ansari will be able to confirm today after lunch time.
VAC:
- Nothing to report.
XPD:
- Not present.
DET:
- XO inquires on the DSSC activities in SCS: DET says it may be delayed a bit due to other activities; DET got a ticket regarding operation; DA believes the DSSC was
running and used.
ITDM:
- Comment on DSSC: it was used but we shall not forget that on the first day there was not a preparation and we could expect hiccups.
- A faulty memory module must be replaced and the exflgateway will be shut down shortly for this activity at around 12:00. An e-mail will be sent but nobody seems against
to it.
XRO:
- Nothing to report.
LAS:
- SA3 AMPHOS photodiodes still has problems. System is partially working and can be operated. LAS knows beam size and pointing do not change but not if loses power.
AMPHOS is contacted.
The consequence is that switching ON and OFF takes more time because it is done manually. Further measurements will be done and SA 3 instruments will be updated
accordingly.
- LAS informs its OCD team is not responsible for synchronization issues.
- SA1 and SA2 lasers are fine.
UNSYS:
- Small issues with SA3 PLC crashes: SA3 is operated without first cells. A re-start of the servers is needed, probably today or tomorrow. UNSYS will inform SCS and SQS
when this is fixed.
SPB:
- Nothing to report.
FXE:
- FXE says that SQS will need to perform some tests: this will be discussed in separate round.
MID:
- All fine.
HED:
- Data recording on Saturday night was not saved. Shift crew realized at the end of the shift that it was not saved - main data for the shift.
- ITDM investigated the issue after ticket arrived yesterday. It confirms data was not recorded and can't see why this happens as ticket arrived late. Even the folder of
the data was not recorded.
For the future: there is an assumption to look at the data every few minutes. ITDM will share procedures. Further discussions on flexibility for different systems/setups
have to be done.
- HED says the 5Hz test must be tomorrow by the morning. XO states that currently this is only a test then we will see what happens. HED has this understanding.
- HED has recorded several hundreds of microns in horizontal jitter. XRO says that it is important to work together for investigating the jitter.
HED will send the data to XRO and/or the coordinator of stability task force.
SCS:
- Not present.
SQS:
- Preparing next week user operation; still some problems with Zoom connection: SQS and ITDM will discuss the issue. |
531
|
17 Jul 2024, 09:50 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.07.2024 |
General Announcement:
- Martin Doering informs today an e-mail will be sent to groups asking for tasks that are cancelled or postponed. The feedback will be required until mid of next week.
- A. Galler informs on a report for non-correct bunch arrival monitors at the instruments. It is requested to instruments to get information on this topic and bring back to XO.
- User Operation Meeting starts next Friday 19.07.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Nothing to report.
VAC:
- Not present.
XPD:
- Gotthard-II in XTD6 Hirex: today the power supply will be checked and by end of the day info to XO/PRC will be done.
DET:
- SPB/SFX an issue with Jungfrau-4M high voltage power supply system happen and is broken needing a fix.
- Hirex/Gotthard-II the tests with beam is prioritized on Monday/Tuesday next week.
ITDM:
- Nothing to report.
XRO:
- On the weekend it starts the technical ramp-up of SA3 and Monday/Tuesday the SA2 and SA1;
- On Monday the SEPS interlock tests are happening and hutches will be closed.
LAS:
- Nothing to report.
- Bunch pattern server issue last week: fix was provided. No more info on the effects of it on LAS preparations.
UNSYS:
- Issue with SA3/cell18 undulator did not move and hit the limit. Under investigation.
SPB:
- Nothing to add to the Jungfrau issue.
FXE:
- Nothing to report.
MID:
- Issue with vacuum system at MID - failed yesterday twice.
HED:
- Nothing to report.
SCS:
- Yesterday problem with mechanics in tunnel; will need PLC team; Leandro Z. informs is under investigation.
SQS:
- Nothing to report.
SXP:
- Not present. |
435
|
17 Jul 2023, 09:53 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.07.2023 |
General Announcement:
- SEPS interlock tests are taking place today. An e-mail was sent to xo-info last Friday containing information about the order of the tests.
CTRL:
- Start with bring up days (SCS and SXP today) the whole week.
- Workaround solution for PLC/Karabo was deployed but needs to be redone tomorrow at 8AM tomorrow. An e-mail will be sent to xo-info.
DA:
- Nothing to report.
EEE:
- Bring up days and support of SEPS.
VAC:
- Nothing to report.
- As PRC, Martin D. says on Saturday morning issues with AIBS blocked beam operation. Solved by DRC and EEE/PLC OCD.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Data analysis of experiments (past ones): to be migrated on next week over three days. E-mail to be sent to xo-info.
XRO:
- Involved in the SEPS interlock today.
- ZZ for HED Mono was successful by power cycling device Not yet clear if camera is broken or a Karabo/PLC issue.
LAS:
- Nothing to report.
UNSYS:
- All fine.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- PP laser work this week and then setting up beamtime for cw31.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Not present. |
522
|
17 Jun 2024, 09:38 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.06.2024 |
General Announcement:
- Summer maintenance is about to start on Wednesday; tomorrow the XRO and XPD ramp down activities are planned.
- The XO Integration meeting continues to happen during the summer maintenance period.
CTRL:
- Nothing to report; preparing for the summer maintenance.
DA:
- Nothing to report and quiet on the OCD side.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing major to report.
ITDM:
- Nothing to report.
- Maxwell maintenance: Likely to be done Monday/Tuesday of last week of June is the deployment. E-Mail will be sent.
XRO:
- Nothing to report.
LAS:
- Nothing to report.
- SA1 issue of last weeks with drifting: sync system maintenance was not announced and found to be the reason for it. Right now it is fixed. Also master time was reset by EEE.
UNSYS:
- Everything fine apart of the SA1/cell22 PS motor to be replaced when tunnels are open.
SPB:
- Not present due to the ongoing retreat.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Start with maintenance tasks.
SQS:
- Nothing to report.
SXP:
- Not present. |
133
|
18 Jun 2020, 13:40 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.06.2020 |
General Announcement:
- Today and tomorrow it takes place the tunnel ventilation maintenance between 6:30 and 8:00AM;
- An e-mail was sent to readiness list with tunnel access restrictions for next Friday morning at the Osdorf Born site in and XTD4 work between 10-11AM.
- Today there the maintenance of the SA3 hutch crane is scheduled.
CTRL:
- CTRL will follow up the uTCA updates.
- Mc2 migration in SA2 is almost done - only XPD needs to test some componenents.
- CTRL is working in some layout problems in scenes of the latest GUI update (new Karabo). Groups are encouraged to write tickets to CTRL if they require changes.
DA:
- Nothing to report.
EEE:
- Shutdown activities are ongoing with, e.g, VAC loop updates and PLC updates;
- The firmware updates affecting the PP-laser timing will take place on next Friday (19.06) in all SASEs.
- EEE is following the delay on the MID cabling related to personal interlock.
VAC:
- Shutdown activities in XTD6 and XTD10 are ongoing.
XPD:
- Currently finishing own summer shutdown tasks in tunnels.
- First DAQ test together with ITDM: had to wait the timing server re-start. To be continued today also after full mc2 migration.
DET:
- Calibrations of detectors at instruments are ongoing.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- So far all in good state.
UNSYS:
- Nothing to report.
SPB:
- DAQ update was not an entire success - but it has been taken care. DAQ is needed for the calibration test of detectors.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Nothing special.
SCS:
- Nothing to report.
SQS:
- PC updates are ongoing.
- SQS raises the question on hutch access during the disabled emergency off planned for next Monday. It is possible that SQS EQP will be in sick leave on that day.
XO will contact Torsten Schoen to get more details on the time schedule and possible access for that day. |
419
|
17 May 2023, 09:40 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.05.2023 |
General Announcement:
- Change in 2024 schedule: for next year the setup days is shifted from Mondays to Tuesdays. Please keep it in mind when setting shift plans for next year.
In case of questions please get in touch with XO.
- Currently we are in facility development week and so far mostly activities linked to the accelerator were done.
- The UOM of next Friday 19.05 does not take place.
CTRL:
- Nothing to report.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Everything running normally.
- Yesterday intervention at XTD6 to move collimator at MID branch: system was moved accordingly to the plan.
XPD:
- Commissioning activities ongoing.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Bringing up the AMPHOS laser and it shall be OK by the end of the week. In case of questions please address Max L.
UNSYS:
- All good.
SPB:
- Nothing to report.
FXE:
- Two vacuum leaks were found at the experiment and fixed together with VAC members.
MID:
- Preparing for experiment next week. MID is in contact with EEE to address some issues.
HED:
- Not present.
SCS:
- Preparing new timing setup.
SQS:
- Nothing to report.
SXP:
- Not present. |
225
|
17 May 2021, 10:25 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.05.2021 |
General Announcement:
- Adrian Mancuso tells on the workaround for the crosstalk between SA1/SA3 documented by Harald Sinn. The idea was to switch off the feedback prior the bunch changes.
Harald S. says that it is not sure if this has worked. Adrian M. says that fir the future this has to be addressed as both SA1 and SA3 would like to change bunch number.
CTRL:
- Follow up from the DOC last week: some cameras in HED started in unexpected states. This has been understood and when the update is ready the deployment has to be
coordinated with HED.
DA:
- From DOC OCDs side only minor issues, that were solved by restarting devices.
EEE:
- Due to the special FD week starting today, there is no DOC this week.
The DRCs (Patrick G. until Thursday and Monica T. from Thursday) will receive the calls: for normal issues, please send a ticket; for urgent cases call the DRCs.
One can also contact directly the individual groups.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Incident at SPB with AGIPD detector: damage to several pixels. The cause for it is not yet known.
The pixel modules have the replaced and the cause relates to intense radiation. It's important to follow up and understand how it happens. SPB will investigate and
communicate findings.
ITDM:
- Nothing to report.
XRO:
- Nothing to report.
LAS:
- Everything good with Lasers.
UNSYS:
- Issue with Quad mover in cell18/SA1 - Suren A. could address it without need of access but further investigations have to be done on-site.
SPB:
- Small injection incident over the weekend.
- Problem with one DAQ: number of pulses was OK but not the values. This was solved by the DOC and some data were wrongly saved for the users (attenuation values).
FXE:
- Timing tool tests at FXE during the night: crosstalk between SA1/SA3. When number of SA1 bunches were changed, the beam pointing was changing in SA3.
So FXE was requested to do not change bunch numbers what hindered the tests.
- LPD issue: progress has been made last week and is being accelerated.
MID:
- Quick warning: until Wednesday some Seeding tests will be ongoing at MID.
HED:
- Successfully experiment last week: HED thank all involved people.
- Addressing CTRL deployment: HED will contact CTRL after this meeting to discuss some details before the deployment action goes on.
- On last Friday at 13:00 one camera corrected configurated did not acquire data and DOC was contacted.
- On Saturday the timing drifted linearly for 0.5ps. HED contacted PRC and DRC and is not yet completely understood.
SCS:
- Nothing to report.
SQS:
- Confirm what FXE has said on the crosstalk with SA1/SA3.
- Sometimes MCP detector was inserted and trigger the EPS to beam stop. Jan G. says that there was a mistake in the interlock configurations for going above 30 bunches.
When SQS wanted to go to 67 bunches it triggered the beam OFF. |
507
|
17 Apr 2024, 09:47 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.04.2024 |
General Announcement:
- A. Galler inform on the transponder/access issues at XHEXP1 last two days: when turnstiles are not working, people shall not get though and enter experimental Hall.
This is a safety break that will be taken by SRP. Please do not enter Hall if turnstiles are not working.
- As DRC, A. Silenzi informs there is nothing to report so far.
CTRL:
- Together with XPD and XRO a new version of DAQ in tunnels was installed and tested. All went fine.
DA:
- Nothing to report.
EEE:
- Nothing to be reported.
VAC:
- Nothing to report. Repair on Monday went successful.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- DAQ Switch in SA3 was exchanged and work fine.
- GPFS update is postponed to a later date (tbd).
XRO:
- SA2 ATT #5 (1.2mm CVD) is replaced and working.
- SA1 mirror is calibrated to work with Euler motions.
- SPB/SFX is aligned with 22keV beam.
LAS:
- Nothing to report.
UNSYS:
- PS motor in SA1/cell23 was replaced yesterday by a ZZ.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
596
|
17 Mar 2025, 09:36 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.03.2025 |
General Announcement:
- As DRC, Jola S.-D. says it was a quiet weekend.
CTRL:
- Nothing to report.
DA:
- Not present.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Nothing to report.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Not present.
UNSYS:
- Nothing to report; all fine.
SPB:
- Nothing to report; all good downstairs.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- All fine at HED;
- Question: possibility to use beam parasitically tomorrow? A. Galler says one can always open the shutter if stability or tuning is not required.
Please contact the PRC for details on status or help with communication with BKR.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Preparing for this week's experiment. |
208
|
17 Mar 2021, 09:15 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 17.03.2021 |
General Announcement:
- nothing.
CTRL:
- LAS reported the pulse statistics did not work properly: re-started systems due to lost connections.
- OCD call related to HED AGIPD test system: fix ongoing.
- Update on train-ID slow data on XGM: CTRL is in touch with Desy and Theo. Question to SPB and XPD: how much effort is needed for that CTRL and ITDM to place the missing information in the run. Involved parts will discuss an agreement by the end of the week. Steffen H. will prepare a summary to inform XPD.
DA:
- no important news.
EEE:
- no important news.
VAC:
- nothing to report.
XPD:
- nothing to report.
DET:
- nothing special.
ITDM:
- all fine.
XRO:
- Not present.
LAS:
Going fine: Laser pattern issue from yesterday was solved by CTRL.
UNSYS:
- Problem on Monday with quad mover cell18/SA1 took 6 hours on ZZ. It is now fixed.
- A problem with undulator segment on cell36/SA1 needs diagnostic and eventual ZZ access. RCs are contacted.
SPB:
- The samples to be used next week are challenging to prepare.
FXE:
- Used beam yesterday. No problems to report.
MID:
- all fine.
HED:
- nothing to report.
SCS:
- nothing to report.
SQS:
- all good. |
588
|
17 Feb 2025, 09:39 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.02.2025 |
General Announcement:
-
CTRL:
- Small report: last week issue with bunch pattern configuration (Karabo reporting error). Seems to be obsolete properties removed from DOOCS were still in Karabo.
Valerii B. is working with DOOCS people and will be ready next days. Device is operational.
DA:
- Couple of calls involving setting data analysis tools.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- All fine with XPD.
DET:
- From DOC: hiccups from one module at LPD. Right now all of them are working. Confirmed by FXE.
ITDM:
- Info today Maxwell servers will be reconfigured. It shall not disturb anyone.
XRO:
- Nothing to report, also from PRC side (Maurizio V.).
LAS:
- Issues with timing card update was solved by EEE.
UNSYS:
- Received 19 OCD calls due to stuck Apple-X undulators during SA3 scans. To understand software bug, one needs time to work with them.
SPB:
- Nothing to report.
FXE:
- Issues with LPD.
- Stuck motor that was not able to be reset (user motor 19). DOC is informed.
MID:
- All fine at MID.
HED:
- Not present.
SCS:
- Nothing to report.
SQS:
- Nothing to report.
SXP:
- Not present. |
200
|
17 Feb 2021, 09:27 |
Arvid Gebhardt | General | Information | Notes XO Integration Meeting 17.02.2021 |
General Announcement:
-
CTRL:
- update for GUI server this morning is finished.
- CTRL advices people starting systems such as cameras, in case of connecting issues please try first to reboot the devices first.
DA:
- nothing special to report.
EEE:
- will update PPL update mTCA SASE3 - affects only LAS group
VAC:
- nothing to report.
XPD:
- Recommissioning diagnostics in SA1.
- Pop-in YAG screen in FXE/SA1 was found broken. Any information on when was working last time please send to Andreas K. In this Pop-in is a second screen with diamond which is working. YAG exchange is for next maintenance period.
DET:
- The offline calibration service update is finished and is available again. Please contact DET in case of issues.
ITDM:
- nothing to report.
XRO:
- Working at BKR yesterday with commissioning SA1 alignment; SA1 is aligned until SPB and FXE.
- Today continuing with SA2 depending on beam stability.
- Idoia F. mentions that computers were not running at BKR. A check after shutdowns and prior operation is welcome.
LAS:
- The AMPHOS in SA3 needs a new power supply. Expected delivery and exchange on Friday.
- PLC update in SA3 and uTCA upgrade on Friday.
- Advancing with SA1-PPL commissioning.
- LAS will send e-mail to Zunaira A. for that MEA3 personal is contacted on the problems with sensor boxes.
UNSYS:
- Ambient field coil was fixed.
- New minimum gaps will be calculated and communicated to XO.
SPB:
- After interlock test last week there is an issue with the new DACHS terminal. The hutches can’t be accessed. Pouneh S. says DACHS is working but this particular new terminal might not be activated in the system. An special permission must be given. Tobias Haas will be informed to contact MEA3.
FXE:
- Martin K. will ask FXE colleagues on YAG screen information. Currently he is not aware when this happens (similar event back in 2019).
MID:
- all fine.
HED:
- all fine.
SCS:
- in contact with Eric B. to get the beam shutter back on Friday for closing hutches during the weekend.
SQS:
- Early next week review with the digitizer engineers.
- Pouneh S. asks that laser interlock in laser hutch does not work. The new parts have been shipped and arrive soon. Together with TS electrician one has to exchange the relay. Daniel Rivas is informed. |
483
|
17 Jan 2024, 09:44 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 17.01.2024 |
General Announcement:
- Functional interlock tests at instruments are ongoing by D3 and SRP. Information was sent by e-mail.
- A. Galler reminds that from this year the machine maintenance and tuning day takes place on Tuesdays.
- The UOM on Fridays will slightly change its program and the report from RC, PRC and DRC will not take place on it but rather on Monday's RC meeting at 10AM.
From January 26th every instrument that receives beam regardless of having users or not will present their status and activities.
For blue weeks the Schenefeld groups using beam will make a brief report together with the Jitter report from instruments. An e-mail with these changes will be sent.
CTRL:
- Progressing with bring up days. SQS was postponed due to sickness and will be done next Monday.
DA:
- Busy with bring up days.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Nothing to report.
DET:
- Busy with bring up days and going smoothly.
ITDM:
- Nothing to report.
XRO:
- Not present.
LAS:
- Nothing to report.
UNSYS:
- Problem with SA1/cell28 undulator: replace of power distribution did not solve the issue. The downstream linear encoder does not work and a switch to rotary encoder is done to allow operation.
Encoder to be fixed in a future maintenance period.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
MID:
- Nothing to report.
HED:
- Busy with bring up days.
SCS:
- Bring up days went fine - thanks to the groups.
SQS:
- Not present.
SXP:
- Bring up days went well on Monday. |