Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 269     Entry time: 18 Oct 2021, 10:14
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 18.10.2021 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- On the mention of offline calibration being slow: DA reminds to call the DOC as soon as the issue occurs. It is hard to find root causes at a later time.

EEE:
- Issue with SCS Scannery: solved during the weekend and follow up further;
- Coax cable installation in FXE to start from this Tuesday 19.10.

VAC:
- Nothing to report.

XPD:
- No issues to report; This week XPD is involved at Hard X-rays activities with 24keV in SA1 and >30keV in SA2.

DET:
- Nothing to report.

ITDM: 
- Nothing to report.

XRO:
- Attempt to measure the beam position in SA2 this morning was missed as machine started to change parameters.

LAS:
- Not present.

UNSYS:
- Nothing to report.

SPB:
- Observed beam drift of up to 2mm on the 17.10; Theo M. confirms that horizontal direction moved up to 7mm at the XGM.

FXE:
- Nothing to add.

MID:
- All fine at MID; successful user beam time; Issues with Laser being helped during the weekend.

HED:
- Agipd-mini half back to HED; checked with DAQ; tests during this week.
- Also calibration for the single shot operation this week (Single shot with Agipd; picking only trains that have signal).
- Weekend to get 30keV beam: Zuzana K. is the main contact for communication and planning. 

SCS:
- Scanner-y issues: it does not run stable (not allowing to be used in automated motion); Beamtime successful.

SQS:
- Nothing to report.