Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 179     Entry time: 18 Nov 2020, 11:23
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 18.11.2020 
General Announcement:
- Updates on the maintenance schedule will be made available in Alfresco. Guidelines in how to integrate calendars will be sent to readiness mailing list, for example.
- Please feel free to contact XO by to share any thoughts related to the Maintenance.

CTRL:
- Successful tests of HED pulser were done on Monday;
- CTRL is preparing Karabo 2.10 deployment: a schedule will be sent around per e-mail. FXE starts on 25/11. Remaining areas take place on Tue/Wed/Thu of week 49. 
SPB will be discussed later due to the AGIPD work.

DA:
- DA has received two messages from CTRL related to Karabo and data analysis deployment: first about deployment and second about bridge.

EEE:
- Nothing to report.

VAC:
- Nothing to report.

XPD:
- XPD is involved on MID tests this week;
- Shimadzu camera tests/development is cancelled due to AGIPD intervention at SPB.

DET:
- Nothing to report.

ITDM: 
- Planning for next week maintenance and working with AGIPD/SPB intervention.

XRO:
- Nothing to report.

LAS:
- Nothing to report.

UNSYS:
- A problem with SA2/cell37 coupler is found and will be fixed during shutdown.

SPB:
- Work on AGIPD is going OK. It has been found the expected minor issues. SPB expects AGIPD experts on site.

FXE:
- Nothing to report.

MID:
- Fast-ADC issue is under investigations together with EEE/Bruno F.

HED:
- Nothing to report.

SCS:
- Not present.

SQS:
- Nothing to report.