SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
|
|
Message ID: 427
Entry time: 19 Jun 2023, 10:08
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 19.06.2023 |
|
|
General Announcement:
- Today is the last day with photon beam operation for the ramp down activities from XRO and XPD. From tomorrow (Tuesday) morning the photon tunnels (XTDs) will be open for the summer maintenance period.
CTRL:
- Starting to deploy Karabo for the summer maintenance; an e-mail will be sent to xo-info list.
DA:
- Nothing to report.
EEE:
- Nothing to report.
VAC:
- Nothing to report.
XPD:
- Together with XRO there is the ramp down day. Check system; support studies from Gianluca/Weilun (XGM and HIREX);
- Start with SA3; then SA1 and SA2.
- Measurements in SA3 (PES / grating spectrometer) take place.
DET:
- Nothing to report.
ITDM:
- As mentioned last week, the closing proposals is taking place; please move the data.
- SA3 will switch to the new storage system / hardware by end of the week / start next week.
Files present at the current online storage system need to be copied - copy is not automatic: info will be sent to xo-info mail.
XRO:
- Working in ramp down day: coordinating with BKR and experiments.
- Priority is to get data for the current situation to address potential issues during the maintenance.
- Reminder to SXP: please close hutch and open shutter; SQS branch ramp down is done; SCS ongoing.
LAS:
- Started with maintenance. Lasers will be OFF in the middle of the week.
UNSYS:
- All fine.
SPB:
- Preparing for maintenance.
- Beamtime last week went fine.
FXE:
- Nothing to add; used beam during the nights last week.
MID:
- Nothing to report.
HED:
- Not present.
SCS:
- Not present.
SQS:
- Nothing to report.
SXP:
- Started on Tuesday: photon energy was bad at 1keV;
- Hutch will be closed today morning. |