ID |
Date |
Author |
Location |
Severity |
Subject |
Text |
|
27
|
01 Apr 2019, 10:29 |
ITDM Admin | General | Information | running jdd panels in control rooms | On all
PCs in the control rooms including BKR and
also on the exflgateway there is a new version |
|
57
|
19 Jun 2019, 16:33 |
ITDM Admin | General | Information | Re: running jdd panels in control rooms | Regarding the recent announcements from
doocs/jddd people about running jddd application
I post here a short summary: |
|
35
|
24 Apr 2019, 10:05 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 24.04.19 | SPB/SFX
SPB/SFX is preparing for
the upcoming beamtime.
CRL motors |
|
45
|
20 May 2019, 10:02 |
Gerd Wellenreuther | General | Information | Status report after dispatch meeting Monday 20.5. 09.30 | SPB/SFX
are working on achieving
a good focus @ 6 keV, which currently is |
|
46
|
22 May 2019, 09:58 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 22.05.19 | FXE
SPB/SFX
XTD2 attenuator |
|
47
|
24 May 2019, 11:01 |
Gerd Wellenreuther | General | Information | Status report after dispatch meeting Friday 24.5. 09.00 | SPB/SFX
are working on achieving
a good focus @ 6 keV, which currently is |
|
48
|
27 May 2019, 10:35 |
Gerd Wellenreuther | General | Information | Status report after dispatch meeting Monday 27.5. 09.30 | SPB/SFX
Digitizers are ready, have
been tested by CAS ==> to be be installed |
|
49
|
29 May 2019, 10:30 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 29.05.19 | FXE
SPB/SFX
XTD2 attenuator appears |
|
51
|
05 Jun 2019, 09:59 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 05.06.2019 | FXE
SPB/SFX
few days of beamtime |
|
78
|
12 Aug 2019, 09:50 |
Gerd Wellenreuther | General | Information | Status report after dispatch meeting 12.8. | XO
FXE
XTD1 CRLs: There is an |
|
79
|
14 Aug 2019, 10:01 |
Gerd Wellenreuther | General | Information | Minutes of the Technical integration meeting 14.08.2019 | XO
On Monday at around 12:20
there was a power glitch at least in Hamburg, |
|
97
|
10 Feb 2020, 10:12 |
Frederik Wolff-Fabris | General | Information | Notes Dispatch meeting Feb 10th, 2020 | SPB: Nothing to report;
FXE: Everything ongoing; nothing special |
|
98
|
17 Feb 2020, 12:02 |
Frederik Wolff-Fabris | General | Information | notes Dipatch Meeting Feb. 17th, 2020 | FXE:
Nothing to report: no issues;
|
|
101
|
10 Mar 2020, 12:44 |
Frederik Wolff-Fabris | General | Information | notes Dipatch Meeting March 9th, 2020 | * Users are scheduled to be here this week
(4 beamlines in user runs). SPB, HED, MID
report several users have cancelled the travel. |
|
102
|
16 Mar 2020, 09:36 |
Frederik Wolff-Fabris | General | Information | Notes Dipatch Meeting March 16th, 2020 | FXE:
- Beamline is in safe state;
- Minor Jungfrau calibration issues over |
|
108
|
06 Apr 2020, 09:50 |
Frederik Wolff-Fabris | General | Information | notes Dipatch Meeting April 6th, 2020 | CTRL:
- It was remotely observed that some cameras
were consuming too much memory. By remotely |
|
111
|
20 Apr 2020, 10:59 |
Frederik Wolff-Fabris | General | Information | Notes Dispatch Meeting 20.04.2020 | General:
- Desy informed a power glitch occurred on
Thursday 16th at 04:55AM. TS has not seen |
|
112
|
23 Apr 2020, 10:04 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 22.04.2020 | General Announcement:
- An e-mail was sent yesterday about the
relaxation of restrictions on the control |
|
113
|
24 Apr 2020, 13:48 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration Meeting 24.04.2020 | Relaxation control network:
- CTRL and XO remind the groups to submit
the planned activities on e.g. scenes, projects, |
|
114
|
28 Apr 2020, 16:19 |
Frederik Wolff-Fabris | General | Information | Notes XO Integration meeting 27.04.2020 | General Announcement:
- The CTRL group has received 3 Control Network
tasks that can be carried out this week;
|
|