Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: notes Dipatch Meeting April 6th, 2020 
CTRL:
- It was remotely observed that some cameras were consuming too much memory. By remotely re-starting these devices the issue was solved.  
- No calls to the OCD during the weekend.

EEE:
- No issues to report;
- Planning a meeting with Instruments/CTRL/DA to discuss long term tasks that have been working on during this reduced operation period.

VAC:
- Nothing to report; All running in good state.

XPD:
- Nothing to report.

DET:
- Nothing to report.

ITDM:
- Nothing to report.

XRO:
- After the recent power glitch: XRO has checked the basic parameters of special motors which presented problems in the past associated to power glitches;
- At this time, the main basic parameters remain OK (note that only few devices were checked - the ones which presented problems in the past);
- During the EuXFEL restart a deeper look on all devices has to be taken together with the instruments. 

SPB:
- Nothing to report.

FXE:
- Nothing to report.

MID:
- Nothing to report.

HED:
- Nothing to report.

	 