Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 114     Entry time: 28 Apr 2020, 16:19
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration meeting 27.04.2020 
General Announcement:
- The CTRL group has received 3 Control Network tasks that can be carried out this week;
- Requests from the groups to Tunnel activities from May 4th are being treated and an answer will come in the next couple of days. 
- With respect to Re-start activities XO/XML has 17 group submissions. We thank the groups to submit them. We have not spotted conflicts so far.
- In case of need to contact staff, please use the working mobiles, emergency phone list or group's mailing lists to address any issue.

CTRL:
- First training on the notification service with 5-6 people. Next training is scheduled for today.

DA:
- All good, doing progress without conflicts.

EEE:
- Nothing special; Group is working on the submission of tasks, to prioritize and make schedule for next week. 
- The group is requested to inform XO in case you have re-start tasks needed to be performed in tunnel.
- An electrical safety person will be provided on site by EEE to serve the instruments from next week. EEE is clarifying and shall respect the safety rules. 

VAC:
- Nothing special. Assembling for the tasks that can be done in tunnel. Also CTRL is involved. Progressing normally.

XPD:
- We have submitted the tasks and looking forward to coordinate with VAC, XRO, EEE to plan the tunnels tasks. 

DET:
- Same as XPD.

ITDM: 
- Nothing to report.

XRO:
- We sent re-start task list. The main problem is to evaluate what work can be done due to safety regulations in the case of complex installations.

LAS:
- We are preparing to switch SA1 on beginning of next week and other lasers will follow during the next week (PP and lab lasers). 
- SA2 may delay due to the needed presence of external company.

SPB:
- Nothing special to report; The group believes it has no activities in the tunnel;

FXE:
- Similar when compared to SPB;

MID:
- Preparing the start-up;

HED:
- Preparing for the start-up.
- HED will need people to switch on electric components on the racks.

SCS:
- Nothing special to report.

SQS:
- Nothing special to report. We are ramping up the vacuum system.