Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther, Page 3 of 29  Not logged in ELOG logo
ID Date Authordown Location Severity Subject Text Attachments
  135   23 Jun 2020, 14:12 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 22.06.2020General Announcement:
- The User & Operation Meeting that took
place at beginning of this year on Fridays
  
  136   25 Jun 2020, 10:27 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 24.06.2020General Announcement:

- Exceptionally next Friday the XO Intergration
  
  137   30 Jun 2020, 08:50 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 29.06.2020General Announcement:
- The Photon Run Coordinator will re-start
next Friday July 3rd. Please also feel free
  
  138   01 Jul 2020, 13:53 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 01.07.2020General Announcement:
- Interlock tests are starting in SASE3 instruments
right now. Zunaira, Eric and Wolfgang Clement
  
  139   03 Jul 2020, 14:21 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 03.07.2020General Announcement:
- The Interlock tests are finished in all
tunnels and XHEXP1 areas, following information
  
  140   07 Jul 2020, 13:23 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 06.07.2020General Announcement:
- Since the end of the shutdown last Friday,
the current Program is "Access/Tuning/Setup";
  
  141   10 Jul 2020, 13:50 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 08.07.2020General Announcement:
- Machine start-up continues to be ahead
of schedule. Beam transmission to T4D and
  
  142   14 Jul 2020, 13:45 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 13.07.2020General Announcement:
- XO will reset the calendar invites for
the XO Integration Meetings of Mondays and
  
  143   17 Jul 2020, 10:19 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 15.07.2020General Announcement:
- SASE3 tuning will start this afternoon
and possibly will last until Thursday afternoon.
  
  144   20 Jul 2020, 14:18 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 20.07.2020General Announcement:
- Regarding Operation, VAC and PRC had a
workaround to restore the North branch beam
  
  150   11 Aug 2020, 11:01 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 10.08.2020General Announcement:
- Beam delivery starts this week. XO reminds
the reason to send the Beam Delivery table
  
  151   12 Aug 2020, 10:52 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 12.08.2020General Announcement:
- Andreas G. thanks all instruments that
have so far sent back to XO the cw35 Beam
  
  153   19 Aug 2020, 12:08 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 18.05.2020General Announcement:
- A. Galler reminds the audience on the daily
informal BKR chat taking place at 15:00:
  
  154   24 Aug 2020, 11:39 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 24.08.2020General Announcement:
- The safety rules require the use of masks
when moving around as well as the limitation
  
  155   26 Aug 2020, 13:49 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 26.08.2020General Announcement:
-  XO is looking forward to receive today
the Delivery and Operator tables from the
  
  156   31 Aug 2020, 11:31 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 31.08.2020General Announcement:
- XO reminds every day at 15:00 there is
an informal BKR chat where one might get
  
  157   02 Sep 2020, 13:33 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 02.09.2020General Announcement:
- If instruments find the machine is not
performing as you expect when comparing to
  
  158   07 Sep 2020, 14:37 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 07.09.2020General Announcement:
- XO thanks instruments and support groups
for using the E-logs while reporting activities.
  
  159   09 Sep 2020, 10:10 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 09.09.2020General Announcement:
- XO reminds the groups to please inform
staff to check for self-rescuer training
  
  160   14 Sep 2020, 15:34 Frederik Wolff-FabrisGeneralInformationNotes XO Integration Meeting 14.09.2020General Announcement:
- None.
  