Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 98
Entry time: 17 Feb 2020, 12:02
|
Author: |
Frederik Wolff-Fabris |
Location: |
General |
Severity: |
Information |
Subject: |
notes Dipatch Meeting Feb. 17th, 2020 |
|
|
FXE:
Nothing to report: no issues;
MID:
Delay line pumping down; Connecting all devices in preparation to be ready for Friday;
EEE:
Finishing SQS interlock scenes and SPB loops;
ELMO parameters lost themselves (in connection to XRO/Maurizio request). Parameters to be checked this week and next shutdown;
XPD ticket to be checked;
Cabling shall be started for SQS/SCS: waiting for open hutch;
CTRL:
Ticket from XPD (shared EEE/CTRL): dry run did not work at BKR: missing pieces.
Please instruments check the systems during the day prior Friday when the Test Run starts;
Request from CTRL/Chris: Define guidelines for the users/support on the ticketing and e-log (who has responsibilities to check devices?).
ITDM:
Ticked from XPD/Liuba: it is a ticket with link (?) to E-log.
* Mc2 motors: XRO needs a list of all motors in order to check configurations. Example: SA3 MONO pre-mirrors with torque set to zero; SA3 exit
slits with wrong settings.
* CTRL reminds the instruments to check devices during working hours prior Friday when the Test Run starts with beam delivery. |