Notes XO Integration Meeting 02.07.2025, posted by Frederik Wolff-Fabris on 02 Jul 2025, 10:03
|
General Announcement:
- M. Doering announces on the LIMP-25:
1. Old's AIBS removal is starting already this week (today), after agreement between Inaki de Diego and instruments;
|
Notes XO Integration Meeting 30.06.2025, posted by Frederik Wolff-Fabris on 30 Jun 2025, 09:58
|
General Announcement:
- M. Doering announces one schedule change on the test of mobile electrical equipment during the LIMP-25:
Company doing it finished Desy premises earlier and from this week they start at EuXFEL in offices and then on the labs. If you have equipment to be tested |
Notes XO Integration Meeting 25.06.2025, posted by Frederik Wolff-Fabris on 25 Jun 2025, 10:27
|
General Announcement:
- Martin Doering informs on the LIMP-25:
1. Friday the summer party takes place; please deliveries with big trucks shall be re-scheduled;
|
Notes XO Integration Meeting 23.06.2025, posted by Frederik Wolff-Fabris on 23 Jun 2025, 10:19
|
General Announcement:
- Martin Doering informs on the LIMP-2025:
1. Tunnels were opened from 7AM today;
|
Notes XO Integration Meeting 18.06.2025, posted by Frederik Wolff-Fabris on 18 Jun 2025, 09:47
|
General Announcement:
- LIMP-25 information: Martin Doering informs:
1. Monday 7AM the tunnels are open but smoke extraction system tests is planned from 8AM to 10AM so that tunnels will be noisy and doors difficult to open; |
Notes XO Integration Meeting 16.06.2025, posted by Frederik Wolff-Fabris on 16 Jun 2025, 09:41
|
General Announcement:
- A. Galler says a second Cryo issue happened on Saturday but it was possible to recovered by 18:00.
- LIMP-25 is about to start in one week. In case of questions please do not hesitate in contacting Martin Doering and XO.
|
Notes XO Integration Meeting 11.06.2025, posted by Frederik Wolff-Fabris on 11 Jun 2025, 09:48
|
General Announcement:
-
|
Notes XO Integration Meeting 04.06.2025, posted by Frederik Wolff-Fabris on 04 Jun 2025, 09:44
|
General Announcement:
-
|
Notes XO Integration Meeting 02.06.2025, posted by Frederik Wolff-Fabris on 02 Jun 2025, 09:51
|
General Announcement:
- The ongoing delivery sees a HXRSS at 12GeV with 1mJ total intensity (~350uJ background).
|
Notes XO Integration Meeting 28.05.2025, posted by Frederik Wolff-Fabris on 28 May 2025, 09:42
|
General Announcement:
-
|
Notes XO Integration Meeting 26.05.2025, posted by Frederik Wolff-Fabris on 26 May 2025, 09:56
|
General Announcement:
- A. Galler mentions the V0 was operated by another group after being interlock on Saturday by a vacuum issue in XTD6 while VAC-OCD was investigating the
issue.
|
Notes XO Integration Meeting 21.05.2025, posted by Frederik Wolff-Fabris on 21 May 2025, 09:36
|
General Announcement:
-
|
Notes XO Integration Meeting 19.05.2025, posted by Frederik Wolff-Fabris on 19 May 2025, 09:42
|
General Announcement:
- Harald Sinn inform on the first lasing for XFELO on Sunday morning shift; 100 bunches in the pulse train was giving synchrotron already on Saturday showing
the cavity was aligned.
|
Notes XO Integration Meeting 14.05.2025, posted by Frederik Wolff-Fabris on 14 May 2025, 09:39
|
General Announcement:
- As PRC, Jan Gruenert reports a problem with fire detection system in XTD4 needed the entire day yesterday to fix and by 18:00 was concluded. The North
branch was
|
Notes XO Integration Meeting 12.05.2025, posted by Frederik Wolff-Fabris on 12 May 2025, 09:36
|
General Announcement:
- Successful delivery last days with exceptional machine performance. From tomorrow we have a FD week followed by a 12GeV week.
|
Notes XO Integration Meeting 07.05.2025, posted by Frederik Wolff-Fabris on 07 May 2025, 09:50
|
General Announcement:
-
|
Notes XO Integration Meeting 05.05.2025, posted by Frederik Wolff-Fabris on 05 May 2025, 09:55
|
General Announcement:
-
|
Notes XO Integration Meeting 30.04.2025, posted by Frederik Wolff-Fabris on 30 Apr 2025, 10:12
|
General Announcement:
- Kimon F. informs that tests for a multi-mode fiber communication in XTD4 have to be scheduled with an external company. XO will organize it.
|
Notes XO Integration Meeting 28.04.2025, posted by Frederik Wolff-Fabris on 28 Apr 2025, 09:44
|
General Announcement:
- From PRC, Maurizio V. and Raul V. have no new things to report, apart of the HXRSS difficult tuning.
- As DRC, Luis Maia says the main points were discussed (see below).
|
Notes XO Integration Meeting 23.04.2025, posted by Andreas Galler on 23 Apr 2025, 09:27
|
General Announcement:
CTRL:
guiserver at MID
backbone services moved to a new machine --> should mitigate the issue
DA: |