Group Selection Page
HELP
Controls Group
ITDM
DET
Vacuum
WP78
FXE
SPB
HED
SQS
SXP
Sample Environment
PSPO
XO
TS
Migrated2Zulip
Archived2PDF
MigratedByGroup
|
|
SCS
Photon Commissioning Team
XRO
DOC
WP74
MID
XO_mig
XO_Operation
|
|
Technical integration and coordination
|
| Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
|
Message ID: 619
Entry time: 11 Jun 2025, 09:48
|
| Author: |
Frederik Wolff-Fabris |
| Location: |
General |
| Severity: |
Information |
| Subject: |
Notes XO Integration Meeting 11.06.2025 |
|
|
General Announcement:
-
CTRL:
- Update concerning broker issues at MID: CTRL would like to update it with the new SPB version for tests in the coming two weeks.
DA:
- Nothing to report.
EEE:
- Nothing directly from EEE;
- P. Gessler update on the 50Hz tests on 17.06: starts at 8AM and the master timing will stop sync with 50Hz.
This produces a short jump of trains but shall automatically return back. When switching sync back again it will also jump once more.
Idea is to test the noise reduction from the 50Kz Mains line and test if one can run without this sync with the 50Hz in future. If things run fine during the test one would run for two days without this
Synchronization.
Directed affected groups are already participating in meetings.
- A. Galler informs there is no plans for FEL beam delivery or tuning/energy change possibility during the 50Hz tests on 17.06.
VAC:
- Everything is going well.
- VAC-OCD got a call from SCS this morning for a change of GATT gas. Please let VAC group knows 1-2 weeks in advance for such changes.
XPD:
- Nothing to report.
DET:
- Incident of DSSC at SCS was investigated and communicated to related people.
ITDM:
- Not present.
XRO:
- Not present.
LAS:
- Not present.
UNSYS:
- Nothing to be reported.
SPB:
- Nothing to report.
FXE:
- Nothing to report.
- D3 tests taking place at FXE from Tuesday late shift.
MID:
- Nothing to report;
- Started with LIMP preparations.
HED:
- Everything fine and using beam for the last IHR.
SCS:
- Last beamtime occurring this week.
SQS:
- Preparing for next week D3 tests with 100W tests (100 pulses at 10mJ)
SXP:
- Not present. |