Technical integration and coordination SASE1 Status and SASE3 Readiness
  Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther  Not logged in ELOG logo
Message ID: 618     Entry time: 04 Jun 2025, 09:44
Author: Frederik Wolff-Fabris 
Location: General 
Severity: Information 
Subject: Notes XO Integration Meeting 04.06.2025 
General Announcement:
-	 

CTRL:
- Nothing to report.

DA:
- Nothing to report.

EEE:
- Nothing to be reported;
- Yesterday Patrick G. received invitation for the meeting on the 50Hz tests on 17.06 taking place at Desy. Patrick G. will forward it to xo-info.

VAC:
- Not present.

XPD:
- Nothing to report.

DET:
- Nothing to report;
- DSSC issue faced last week: problem was solved; S. Hauf said the follow up was taking place Friday afternoon together with SCS by debugging the detector.

ITDM: 
- Nothing to report.
- A. Galler saw issues while logging in Fast-X and will discuss with J. Szuba on it.

XRO:
- No issues to report.

LAS:
- Not present.
- LIMP activities: instruments that requested use of PP-laser during LIMP shall be secured. Otherwise please contact XO.

UNSYS:
- Positioning HXRSS crystal showed a lost communication in DOOCS server: solved;
- PS in SA2 cell10 was stuck yesterday and is also solved.

SPB:
- Nothing to report.

FXE:
- Not present.

MID:
- Nothing to report.

HED:
- Everything seems to be fine at HED.

SCS:
- Not present.

SQS:
- Nothing to report.

SXP:
- Not present.