Technical integration and coordination
SASE1 Status and SASE3 Readiness
|
Technical integration and coordination logbook, Contact: A. Violante, G. Wellenreuther |
Not logged in |
 |
|
Message ID: 633
Entry time: 30 Jul 2025, 09:22
|
Author: |
Andreas Galler |
Location: |
General |
Severity: |
Information |
Subject: |
Notes XO Integration Meeting 30.07.2025 |
|
|
General Announcement:
- electrical meintenance on July 30th XHQ green marked area
- electrical maintenance on July 31st - Aug 1st XHQ blue marked area
CTRL:
- issue with fastADC device, investigation going on together with EEE
DA:
EEE:
- Bruno clarifies that the fast ADC issue is with a specific class of the PPL fast ADCs
VAC:
- nothing
- Daniele reports that the SA3 ODL chamber had been m XTD4 ODL
XPD:
- question to SCS and EEE, is the PLC loop 1 up? Nerea comments, yes it is.
DET:
- still investigating the damages on the reference detector and the pulsed x-ray source
ITDM:
XRO:
- tunnel temperature being monitored
- XTD9 lower than the other tunnels, but tolearable for tunnel works
LAS:
- SA2 & SA2 PPLs restarted. SA1 coming later this week
- support from EEE, CTRL is greatly appreciated
UNSYS:
- SA2 Undulators shifted to make toom for the chicances
SPB/SFX
- work ongoing, prep for AGIPD4M (possible installation by end of October)
FXE:
MID:
HED:
SCS:
- XGM restart today afternoon
SQS:
SXP:
DRC
PRC
AOB:
- Michael Prollius reminds to take self rescuers along when leaving the tunnels.
|